✨ Road Construction Estimate
ESTIMATE OF THE COST OF PITCHING AND METALLING THE
MATAURA ROAD FROM TOWN BELT TO MAVIS BRIDGE WAIOPAI RIVER.
Norm.—It is proposed to pitch the road 16 feet wide with 6 inch pitchers, and metal same 17 feet wide with 2½ inch gauged metal, to be laid 5 inches thick: viz., 2 stones thick for first coating. These calculations are arrived at in the following manner:
That two horses will travel 25 miles, and cost 5s. per day; two horses in drays to take 1½ yard per load; two horses on tramway to take 10 yards each trip.
Cost of constructing road, if stone is carted with drays:
Pitchers.—Filling and discharging 7492 cubic yards
. . . . . . . .
Carting 7492 cubic yards
. . . . . . . .
Setting pitchers, 7492 cubic yards
. . . . . . . . £11,088 5 6
Metal.—Filling and discharging 6650 cubic yards
. . . . . . . .
Spreading metal, 6650 cubic yards
. . . . . . . .
Carting 6650 cubic yards
. . . . . . . .
Formation of road, including all culverts, drains, &c., 383 chains
Cost of constructing road, if stone be conveyed by tramway:
Pitchers.—Filling and discharging 7492 cubic yards
. . . . . . . .
Hauling 7492 cubic yards
. . . . . . . .
Setting pitchers, 7492 cubic yards
. . . . . . . . £3,672 6 11½
Metal.—Filling and discharging 6650 cubic yards
. . . . . . . .
Hauling 6650 cubic yards
. . . . . . . .
Spreading metal, 6650 cubic yards
. . . . . . . .
Formation of road, including all culverts, drains, &c., 383 chains
Constructing tramway, 6 miles
Trams, 20 No.
. . . . . . . . .
Balance in favour by conveying stone by tramway, including cost of same ... £2,535 19 6
Next Page →
✨ LLM interpretation of page content
🏗️ Estimate for Pitching and Metalling the Mataura Road
🏗️ Infrastructure & Public WorksRoad construction, Pitching, Metalling, Cost estimate, Mataura Road, Waipai River
Southland Provincial Gazette 1863, No 62