ESTIMATE OF COST OF CONSTRUCTING ROAD FROM BRIDGE WEST END OF WAKIWI BUSH, TO CLARK’S CROSSING.

Note.—Material can be conveyed from the Mokomoko as far as Clark’s Bridge by Punts.

Formation, including culverts, &c., 80 44 chains
Quarrying 1580 yards rubble
Quarrying and breaking 1400 yards metal
Conveying by punt from Mokomoko to Clark’s Bridge, 2980 cubic yards
Discharging and filling 2980 cubic yards into drays
Setting pitchers, 1580 yards
Spreading metal, 1400 yards

... £2,448 11 1

If this road be gravelled, I estimate the cost at—

Formation, &c., 80 44 chains
Gravelling (screened), 80 44 chains

... £1,287 0 9



Next Page →



Online Sources for this page:

VUW Te Waharoa PDF Southland Provincial Gazette 1863, No 62





✨ LLM interpretation of page content

🏗️ Estimate for Road Construction from Wakiwi Bush to Clark’s Crossing (continued from previous page)

🏗️ Infrastructure & Public Works
Road construction, Culverts, Quarrying, Metal, Punts, Mokomoko, Clark’s Bridge, Wakiwi Bush