WALLACETOWN AND RIVERTON ROAD.
ESTIMATE OF THE COST OF MAKING VIABLE THE ROAD FROM WALLACETOWN TO RIVERTON.
Between Bridge No. 1 across the Tomoporaki River the road is fearfully boggy, and I would suggest that the same be drained, formed, and gravelled for some 60 chains ... per estimate.
Forming, gravelling, bridging, and ditching approaches have been formed for:
First culvert (beyond Fraser's Paddock): Approaches have been formed for about 12 chains; this portion will require to be re-formed and gravelled ...
Second culvert: Approaches have been formed for about 4 1/2 chains; the same require to be re-formed and gravelled ...
Third culvert (large): Approaches partially embanked; with require re-forming and gravelling for 18 chains ...
Fourth culvert: Approaches, about 18 chains in length; require to be raised and gravelled, and the ditches cleaned out ...
Fifth culvert: Approaches about 20 chains; require re-forming and gravelled ...
Sixth culvert (at Bush): Approaches, about 10 chains; should be re-formed and gravelled ...
Seventh culvert (beyond Bush, between fences): Approaches, about 34 chains; its first culvert beyond Bush to clean out the drains, re-form, and gravel for that distance ...
Second culvert: Approaches, about 8 chains in length (formed 5 chains and embanked 3 chains), require to be re-formed and gravelled ...
Flat between Terrace and the Waimatuku River is crab-holey, consequently very dangerous to travel upon, and should be drained, formed, and gravelled for about 12 chains, and a bridge built across the River of a span of say 50 feet ...
First culvert (beyond River): Approaches, about 3 chains; require to be embanked and gravelled ...
Second culvert: Present approaches, about 34 chains, require to be raised and extended for a distance of say 30 chains, and gravelled ...
Third culvert (across Creek): Requires to have approaches raised and gravelled for about 6 chains ...
Fourth culvert: Approaches, about 5 chains, require to be raised and gravelled ...
Fifth culvert: The approaches, some 6 chains in length, should be raised and gravelled ...
Sixth and seventh culverts: Approaches, about 20 chains, ought to be re-formed and gravelled ...
Eighth culvert: Approaches (cutting and embankment), for some 8 chains, should be re-formed and gravelled ...
Ninth culvert (near Bush, bottom of Terrace): Approaches, about 1 1/2 chains, ought to be re-formed and gravelled ...
Bridge at Harrier Farm: This has lately been constructed, and I think it advisable to extend the approaches for say 20 chains, and gravel the same.
First culvert: The crossing has been laid with timber and fascines for about 2 chains, which should be gravelled ...
Second culvert: Approaches for about 1 1/2 chains, have been fascined, and now require gravelling ...
Third culvert (gateway): Approaches have been fascined for about 2 1/2 chains and should be gravelled ...
Fourth culvert: Approaches for some 4 chains, require gravelling ...
Fifth culvert: 1 chain requires to be gravelled ...
Sixth culvert (near Riverton): Approaches require to be raised and a new culvert reconstructed, and the same gravelled for a distance of 4 chains ...
Add for unforeseen contingencies ...
Next Page →
β¨ LLM interpretation of page content
ποΈ
Estimate for Wallacetown and Riverton Road Construction
(continued from previous page)
ποΈ Infrastructure & Public WorksRoad construction, Drainage, Gravelling, Culverts, Bridges, Wallacetown, Riverton, Tomoporaki River, Waimatuku River
Southland Provincial Gazette 1863, No 62