ESTIMATE OF THE COST OF MAKING VIABLE FOR NEXT WINTER’S TRAFFIC THE MABEL DISTRICT ROAD VIA RACE COURSE, COMMENCING AT WALLACETOWN ROAD JUNCTION WITH THE NORTH ROAD, AND RUNNING EAST AS FAR AS THE WHEATWOOD CREEK, AND FROM THENCE RUNNING SOUTH TO THE MATAURA ROAD.
I am of opinion that it would be judicious to pitch and metal the approaches to culverts on this road as far as the Waikivi Creek, and that the material for same be conveyed as far as the junction of this with North Road by tramway, where it should be deposited, and carted from thence to where it may be required. The other approaches to culverts beyond this, I would suggest they be all re-formed and gravelled (with clean gravel), giving the road a good crown.
Pitching, metalling, and re-formation of road as follows, not including cost of materials delivered at Jetty:
CULVERTS AND BRIDGES
- Forming 5 chains ...
- Re-forming 18 chains ...
- Pitching 23 chains, 14 feet by 6 inches ...
- Metalling 28 chains, 14 feet by 5 inches ...
- Re-forming 2 chains ...
- Pitching 2 chains, 14 feet by 6 inches ...
- Metalling 2 chains, 14 feet by 6 inches ...
- Re-forming 6 chains ...
- Pitching 6 chains, 14 feet by 6 inches ...
- Metalling 6 chains, 14 feet by 6 inches ...
- Re-forming 3 chains ...
- Pitching 3 chains, 14 feet by 6 inches ...
- Metalling 3 chains, 14 feet by 5 inches ...
- Embanking, etc., 24 chains ...
- Pitching 24 chains, 14 feet by 6 inches ...
- Metalling 24 chains, 14 feet by 5 inches ...
- Re-forming 1 chain ...
- Gravelling 14 feet by 9 inches ...
- Re-forming 2 chains ...
- Gravelling 14 feet by 9 inches ...
- Re-forming 2 chains ...
- Gravelling 14 feet by 9 inches ...
£649 7 3
ROAD FROM WHEATWOOD CREEK
- Re-forming 10 chains ...
- Gravelling 14 feet by 9 inches ...
- Re-forming 6 chains ...
- Gravelling 14 feet by 9 inches ...
- Re-forming embankment, 19 chains ...
- Gravelling 14 feet by 9 inches ...
- Re-forming 2 chains ...
- Gravelling 14 feet by 9 inches ...
- Constructing new culvert ...
- Formation, etc., 1½ chains ...
- Gravelling 14 feet by 9 inches ...
- Re-forming 8 chains ...
- Gravelling 14 feet by 9 inches ...
- Re-forming 14 chains ...
- Gravelling 14 feet by 9 inches ...
- Re-forming 2 chains ...
- Gravelling 14 feet by 9 inches ...
£481 2 6
Next Page →
✨ LLM interpretation of page content
🏗️
Estimate for Mabel District Road Construction
(continued from previous page)
🏗️ Infrastructure & Public WorksRoad construction, Pitching, Metalling, Gravelling, Culverts, Bridges, Mabel District, Wallacetown Road, North Road, Waikivi Creek, Wheatwood Creek, Mataura Road
Southland Provincial Gazette 1863, No 62