WALLACETOWN AND WINTON BUSH.
ESTIMATE OF THE COST OF CONSTRUCTING ROAD BETWEEN WALLACETOWN AND WINTON BUSH, 14 MILES, INCLUDING COST OF CONSTRUCTING TRAMWAY, FOR TRANSPORTING RUBBLE FOR PITCHING, AND TOP METAL.
In this Estimate it is assumed that Mokomoko stone can be discharged from Lighters at Upper Ferry, New River.
The dimensions assumed are—Pitching 20 feet wide, 9 inches in centre, 5 inches at sides, top metal and gravel, 6 inches x 22 feet.
TRAMWAY.
14 miles ... ... ... ... ... ... ... £10,930 0 0
16 trams ...
FORMATION.
920 chains ...
200 chains ...
PITCHING.
31,360 cubic yards, average lead, 7½ miles
Loading ... ...
Discharging and setting ... ... ... ... ... ... ... £21,060 0 0
TOP METAL.
26,460 cubic yards, average lead 6 miles 50 chains
Loading ...
Discharging and spreading ... ... ... ...
GRAVEL.
3,780 cubic yards removing and respreading
Contractors’ profits and contingencies ... ...
Rubble for pitching, delivered at New River Upper Ferry, 31,360 cubic yards ... ... ... ... ... ... ... £56,635 0 0
Top metal, ditto ditto ...
If this is adopted a sum of £13,722 13s must be deducted from Estimate for Great North Road from Wallacetown to Oreti, part of road being mentioned in both Estimates.
Next Page →
✨ LLM interpretation of page content
🏗️
Estimate for Wallacetown to Winton Bush Road Construction
(continued from previous page)
🏗️ Infrastructure & Public WorksRoad construction, Tramway, Pitching, Top metal, Gravel, Rubble, Cost estimate, Wallacetown, Winton Bush
Southland Provincial Gazette 1863, No 62