✨ Road and Public Works Report
8th. From Hill’s Accommodation House to Winton Bush, 258 chains.
Limestone for pitchers to be obtained from near Hill’s.
Average lead, 150 chains.
Leading 7,224 cubic yards pitchers ...
Quarrying ...
Filling ...
Discharging and setting ...
Gravel, 6,857 cubic yards; removing and respreading ...
Forming road, 8m., 66f.
Contractors’ profits and contingencies ... £6,252 19 0
9th. Road through Winton Bush, about 100 chains.
Constructing corduroy ... £2,000 0 0
10th. From Winton Bush, for 140 chains to southward.
Limestone for pitchers to be obtained from near Hill’s.
Average lead, 440 chains.
Leading 8,920 cubic yards pitchers ...
Quarrying ...
Filling ...
Discharging and setting ...
Gravel, 3,780 cubic yards; removing and respreading ...
Trimming road, &c., &c.
Contractors’ profits and contingencies ... £7,423 8 0
11th. Culverts’ approaches between Winton Bush and Wallacetown,
about 60 chains in all. Pitching with Mokomoko stone.
Estimated cost delivered at New River Upper Ferry:
1830 cubic yards
Leading do.; average lead, 640 chains
Leading, discharging, and setting do.
Gravel, 1620 cubic yards; average lead, about 160 chains
Setting and filling
Discharging and respreading
Trimming road
Contractors’ profits and contingencies ... £34,975 3 5
Next Page →
✨ LLM interpretation of page content
🏗️
Road and Public Works Report for Southland Province
(continued from previous page)
🏗️ Infrastructure & Public WorksRoads, Public Works, Southland, Bridges, Drainage, Traffic, Engineering, Contracts
Southland Provincial Gazette 1863, No 62