✨ Electricity Industry Notices
NEW ZEALAND GAZETTE, No. 167
12 DECEMBER 2013
2. Exemption
Exemption—AccuCal Limited (“AccuCal”) is exempted from complying with clause 1(1)(a) of Schedule 10.5 of the Electricity Industry Participation Code 2010 (“Code”) in respect of providing its initial metering equipment provider (“MEP”) audit by 28 February 2014.
3. Term
This exemption expires at the close of 30 April 2014.
4. Reasons for granting the exemption
The reasons for granting this exemption are:
(a) granting the exemption meets the requirements in section 11(2) of the Act for granting exemptions;
(b) by conducting its initial MEP audit at the same time as its authorised test house audit, AccuCal will avoid compliance costs and will minimise disruption to staff involved in audit reviews;
(c) once the exemption expires, the timing of AccuCal’s next MEP audit will be calculated from the date of the MEP audit completed during the period of the exemption; and
(d) the exemption will have little or no impact on other participants and service providers, and will not affect any other Code provisions.
Dated at Wellington this 9th day of December 2013.
For and on behalf of the Electricity Authority:
DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority.
au7946
Notice of Adoption of Replacement Security of Supply Forecasting and Information Policy
-
Pursuant to clause 5(c) of Schedule 1 of the Electricity Industry Act 2010 (“Act”), I give notice that the Electricity Authority (“Authority”) adopts a replacement Security of Supply Forecasting and Information Policy for the purposes of clause 7.4 of the Electricity Industry Participation Code 2010 (“Code”).
-
The adoption of the Security of Supply Forecasting and Information Policy has effect from 16 December 2013.
-
The Security of Supply Forecasting and Information Policy is a document incorporated by reference into the Code as having legal effect in accordance with section 32 of the Act.
-
A copy of the Security of Supply Forecasting and Information Policy and the Code is available on the Authority’s website at
www.ea.govt.nz/act-code-regs/code-regs/the-code/
- A copy of the Security of Supply Forecasting and Information Policy and the Code may also be inspected free of charge or purchased from the Electricity Authority, Level 7, ASB Bank Tower, 2 Hunter Street, Wellington.
Dated at Wellington this 9th day of December 2013.
DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority.
au7959
Notice of Adoption of Replacement Policy Statement
-
Pursuant to clause 5(c) of Schedule 1 of the Electricity Industry Act 2010 (“Act”), I give notice that the Electricity Authority (“Authority”) adopts a replacement policy statement for the purposes of clause 8.10 of the Electricity Industry Participation Code 2010 (“Code”).
-
The adoption of the policy statement has effect from 16 December 2013.
-
The policy statement is a document incorporated by reference into the Code as having legal effect in accordance with section 32 of the Act.
-
A copy of the policy statement and the Code is available on the Authority’s website at
www.ea.govt.nz/act-code-regs/code-regs/the-code/
- A copy of the policy statement and the Code may also be inspected free of charge or purchased from the Electricity Authority, Level 7, ASB Bank Tower, 2 Hunter Street, Wellington.
Dated at Wellington this 9th day of December 2013.
DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority.
au7958
Notice of the Electricity Industry Participation (Modified Dispatchable Demand) Code Amendment 2013
-
Pursuant to section 38(3)(b) of the Electricity Industry Act 2010, the Electricity Authority gives notice of the making of the Electricity Industry Participation (Modified Dispatchable Demand) Code Amendment 2013.
-
The amendment (except for clause 4) comes into force at 1.30pm on 15 May 2014. The amendment amends Parts 1, 13, 14, and 15 of the Electricity Industry Participation Code 2010 (“Code”) to implement a dispatchable demand proposal, to enable demand-side participants at grid exit points to respond to wholesale market conditions by electing to bid load to be dispatched.
-
Clause 4 of the amendment comes into force on 30 April 2014 and revokes the Electricity Industry Participation (Dispatchable Demand) Code Amendment 2011* and the Electricity Industry Participation (Dispatchable Demand) Code Amendment 2011, Amendment 2013†.
-
A copy of the amendment, the revoked amendments, and the Code is available on the Electricity Authority’s website at
www.ea.govt.nz/act-code-regs/code-regs/
- A copy of the amendment, the revoked amendments, and the Code may also be inspected free of charge or purchased from the Electricity Authority, Level 7, ASB Bank Tower, 2 Hunter Street, Wellington.
Dated at Wellington this 9th day of December 2013.
DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority.
*New Zealand Gazette, 20 October 2011, No. 159, page 4557
†New Zealand Gazette, 16 May 2013, No. 57, page 1693
au7944
Notice of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013
-
Pursuant to section 38(3)(b) of the Electricity Industry Act 2010, the Electricity Authority gives notice of the making of the Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013.
-
This amendment comes into force on 24 March 2015.
-
The amendment replaces Part 14 of the Electricity Industry Participation Code 2010 (“Code”) with a new Part 14 and Part 14A, and makes consequential changes to other parts of the Code. The amendment changes the prudential requirements for participants, and changes the clearing and settlement processes carried out by the clearing manager.
-
A copy of the amendment and the Code is available on the Electricity Authority’s website at
www.ea.govt.nz/act-code-regs/code-regs/
- A copy of the amendment, the revoked amendments, and the Code may also be inspected free of charge or purchased from the Electricity Authority, Level 7, ASB Bank Tower, 2 Hunter Street, Wellington.
Dated at Wellington this 9th day of December 2013.
DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority.
Next Page →
✨ LLM interpretation of page content
🏭 Exemption for AccuCal Limited
🏭 Trade, Customs & Industry9 December 2013
Electricity, Exemption, AccuCal Limited, Certification, Electricity Authority
- ,
- DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority
🏭 Adoption of Replacement Security of Supply Forecasting and Information Policy
🏭 Trade, Customs & Industry9 December 2013
Electricity, Policy, Security of Supply, Electricity Authority
- ,
- DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority
🏭 Adoption of Replacement Policy Statement
🏭 Trade, Customs & Industry9 December 2013
Electricity, Policy, Electricity Authority
- ,
- DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority
🏭 Electricity Industry Participation (Modified Dispatchable Demand) Code Amendment 2013
🏭 Trade, Customs & Industry9 December 2013
Electricity, Code Amendment, Dispatchable Demand, Electricity Authority
- ,
- DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority
🏭 Electricity Industry Participation (Settlement and Prudential Security) Code Amendment 2013
🏭 Trade, Customs & Industry9 December 2013
Electricity, Code Amendment, Settlement, Prudential Security, Electricity Authority
- ,
- DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority
NZ Gazette 2013, No 167