β¨ Electricity Reliability Performance Measures
13 AUGUST NEW ZEALAND GAZETTE 2295
- System Average Interruption Frequency Index (SAIFI)
Total Interruptions 1998/99 1997/8 1996/7 1995/6
3.73 1.91 2.53 3.75
- SAIFI Targets for 1999/2000
Planned Interruptions 1999/2000
Unplanned Interruptions 0.55
Total Interruptions 2.18
2.73
- SAIFI Future Targets (Average for the next 5 years)
Planned Interruptions 1999/2004
Unplanned Interruptions 0.60
Total Interruptions 2.10
2.70
-
SAIFI per Interruption Class
1998/9 1997/8 1996/7 1995/6Planned Transpower 1.00 0 1.00 1.00
Planned CHB Power 0.55 0.11 0.17 0.94
Unplanned CHB Power 2.18 0.8 1.36 1.82
Unplanned Transpower 0 75 0 0
Unplanned CHB Power Generation 0 0 0 0
Unplanned Other Generators 0 0 0 0
Unplanned Other Line Owner 0 0 0 0
Planned Other Line Owner NA NA NA NA
Other Interruptions 0 NA NA NA
Next Page →
PDF embedding disabled (Crown copyright)
View this page online at:
VUW Te Waharoa —
NZ Gazette 1999, No 95
NZLII —
NZ Gazette 1999, No 95
β¨ LLM interpretation of page content
ποΈ
Reliability Performance Measures
(continued from previous page)
ποΈ Infrastructure & Public Works31 March 1999
Electricity, Reliability, Performance Measures, SAIFI, Interruption Frequency, SAIFI Targets, Planned Interruptions, Unplanned Interruptions