✨ Electricity Reliability Performance Measures
2296
NEW ZEALAND GAZETTE
No. 95
- Consumer Average Interruption Duration Index (CAIDI)
Total Interruptions
| 1998/99 | 1997/8 | 1996/7 | 1995/6 |
|---|---|---|---|
| 132 | 71.6 | 158 | 140 |
- CAIDI Targets for 1999/2000
Planned Interruptions 115
Unplanned Interruptions 86
Total Interruptions 92
- CAIDI Future Targets (Average for the next 5 years)
Planned Interruptions 102
Unplanned Interruptions 88
Total Interruptions 91
- CAIDI per Interruption Class
| Interruption Class | 1998/9 | 1997/8 | 1996/7 | 1995/6 |
|---|---|---|---|---|
| Planned Transpower | 240 | 0 | 240 | 240 |
| Planned CHB Power | 116 | 144 | 208 | 121 |
| Unplanned CHB Power | 86 | 106 | 91 | 93 |
| Unplanned Transpower | 0 | 75 | 0 | 0 |
| Unplanned CHB Power Generation | 0 | 0 | 0 | 0 |
| Unplanned Other Generators | 0 | 0 | 0 | 0 |
| Planned Other Line Owner | 0 | NA | NA | NA |
| Other Interruptions | 0 | NA | NA | NA |
PUBLISHED BY AUTHORITY OF DEPARTMENT OF INTERNAL AFFAIRS:
LEGISLATION DIRECT, WELLINGTON, NEW ZEALAND—1998
ISSN 0111-5650
Price $3.95 (inc. G.S.T.)
32214—99A
PDF embedding disabled (Crown copyright)
View this page online at:
VUW Te Waharoa —
NZ Gazette 1999, No 95
NZLII —
NZ Gazette 1999, No 95
✨ LLM interpretation of page content
🏗️
Reliability Performance Measures
(continued from previous page)
🏗️ Infrastructure & Public Works31 March 1999
Electricity, Reliability, Performance Measures, CAIDI, Interruption Duration, CAIDI Targets, Planned Interruptions, Unplanned Interruptions