Electricity Easement Rights and Obligations




NEW ZEALAND GAZETTE, No. 77 — 1 SEPTEMBER 2016

culverts and bridges) on the Easement Area, the Accessway and, if clause 2.1(e) applies, any other part of the Land;

i. to clear and keep clear the Easement Area, the Accessway and any routes used by Transpower under clause 2.1(e) of vegetation (including trees), structures (including fences and utility structures), soil, earth, gravel and stone;

j. to trim or remove any tree from the Land located outside the Easement Area if:
i. all or part of the tree breaches or, when fully grown, is likely to breach any legal requirement (including any statute, regulation or code of practice) applying from time to time regarding vegetation near the Line; or
ii. clause 2.1(j)(i) does not apply to a tree but Transpower considers that all or part of the tree is or, when fully grown, is likely to be a danger or hazard to the safety or operation of the Line, provided that Transpower must obtain the Landowner’s prior consent except in an Emergency; and

k. when Transpower undertakes any works under this Easement, Transpower may:
i. excavate the Easement Area, the Accessway and, if clause 2.1(e) applies, any other part of the Land, and remove vegetation (including trees), soil, earth, gravel and stone from the Easement Area;
ii. temporarily exclusively occupy any part of the Easement Area, the Accessway and, if clause 2.1(e) applies, any other part of the Land, including temporarily fencing off the occupied area and temporarily preventing or restricting the Landowner’s access to the occupied area;
iii. construct temporary hurdles and other temporary improvements on the Easement Area, the Accessway and, if clause 2.1(e) applies, any other part of the Land in order to allow the works to be undertaken safely and efficiently; and
iv. remove water from the Easement Area, the Accessway and, if clause 2.1(e) applies, any other part of the Land, and discharge that water onto the Land but Transpower must first consult with the Landowner about the discharge of that water and obtain any necessary environmental approvals for the discharge of water.

l. Transpower does not have the right to:
i. upgrade the Line to have a nominal operating voltage greater than the voltage specified in the Maximum Design Specifications;
ii. construct more permanent poles forming part of the Line than the number specified in the Maximum Design Specifications;
iii. relocate any pole forming part of the Line, but this clause does not prevent Transpower from relocating a pole in a catastrophic failure or to replace the pole, in which case the replacement pole must be located immediately adjacent to the existing pole site and must be located on the Easement Area (unless the parties agree otherwise);
iv. increase the number of electricity circuits forming part of the Line to more than the number specified in the Maximum Design Specifications; or
v. construct any towers to form part of the Line.

3. Transpower’s Obligations

3.1 When Transpower enters the Land, Transpower must:

a. respect and have regard to the Landowner’s use of the Land;

b. try to minimise disruption to the Landowner’s use of the Land;

c. restore any part of the surface of the Land that Transpower damages to as close to its prior condition as reasonably practicable and repair any other direct physical damage Transpower causes;

d. use Transpower’s best endeavours to prevent the outbreak and spread of fire; and

e. remove any debris Transpower creates in undertaking any works and otherwise leave any work sites in a tidy condition.

88



Next Page →



Online Sources for this page:

Gazette.govt.nz PDF NZ Gazette 2016, No 77





✨ LLM interpretation of page content

🗺️ Electricity Easement in Gross Taken — GOR–TEE A Transmission Line Project, Gore District (continued from previous page)

🗺️ Lands, Settlement & Survey
18 August 2016
Electricity Easement, Transmission Line, Gore District, Transpower, Rights, Obligations, Access Tracks, Notices, Land Use Obligations