Electricity Easement Proclamation




NEW ZEALAND GAZETTE, No. 77 — 1 SEPTEMBER 2016

ii. where the Line is or may be electrically unsafe; or

iii. involving an existing or potential electricity outage;

d. "Equipment" includes cables, lines, wires, cranes, drilling rigs, plant, tools and machinery and all material and items required for the purpose of exercising any of Transpower’s rights under this Easement but, to avoid doubt, excludes any culverts and bridges constructed by Transpower under clause 2.1(h);

e. "Land" means the land described as Lots 2 and 3 DP 11793 (Computer Freehold Register SL8B/36);

f. "Line" means an electricity transmission line including all or any part of that line, including:

i. electricity conductors, wires and earthwires;

ii. poles, foundations, ground stays and supports;

iii. insulators, repeaters, devices, appliances, antennas and metering devices; and

iv. other apparatus, structures, fixtures and Equipment which Transpower considers necessary or useful to give effect to Transpower’s rights and obligations under this Easement;

g. "Maximum Design Specifications" means the following details of the Line:

i. The nominal operating voltage is 220 kilovolts;

ii. the maximum number of permanent poles is two; and

iii. the maximum number of circuits is two;

h. "Vehicles" includes four wheel drives, motorbikes, cars and trucks, tractors, trailers, graders, pile drivers, drilling rigs, cranes, helicopters, aircraft, excavation and earthmoving equipment, whether wheeled or tracked; and

i. "Working Day" means any day of the week excluding Saturday, Sunday, national statutory holidays and the anniversary days commonly observed in Wellington and the locality in which the Land is situated.

  1. Interpreting this Easement

13.1 In this Easement, unless the context requires otherwise:

a. singular includes plural and vice versa;

b. headings in this Easement are inserted for convenience only and are to be ignored when interpreting a clause; and

c. derivations of defined terms have similar meanings to the defined terms.

Given under the hand of His Excellency the Governor-General of New Zealand and issued under the Seal of New Zealand this 18th day of August 2016.

[L.S.]

HON LOUISE UPSTON, Minister for Land Information.

GOD SAVE THE QUEEN!

(LINZ CPC/2015/18281)

2016-ln4961

Electricity Easement in Gross Taken—GOR–TEE A Transmission Line Project, Gore District

LT GEN THE RT HON SIR JERRY MATEPARAE,
Governor-General

A Proclamation

Pursuant to section 186(2) of the Resource Management Act 1991 and section 26 of the Public Works Act 1981, I, Lieutenant General The Right Honourable Sir Jerry Mateparae, Governor-General of New Zealand, hereby declare the easement in gross over the land described in the First Schedule to be taken for the GOR-TEE A Transmission Line Project and vested in Transpower New Zealand Limited on the 14th day after the date of the publication of this Proclamation in the New Zealand Gazette.

The terms of the easement are set out in the Second Schedule.

86



Next Page →



Online Sources for this page:

Gazette.govt.nz PDF NZ Gazette 2016, No 77





✨ LLM interpretation of page content

🗺️ Electricity Easement in Gross Taken — GOR–TEE A Transmission Line Project, Gore District (continued from previous page)

🗺️ Lands, Settlement & Survey
18 August 2016
Electricity Easement, Transmission Line, Gore District, Transpower, Rights, Obligations, Access Tracks, Notices, Land Use Obligations