Pursuant to clauses 2.6(4) and (5) of Land Transport Rule: Vehicle Equipment 2004, and under delegated authority, I, Hugh Cameron Matheson, Principal Engineer Vehicles, NZ Transport Agency, hereby approve the LPG fuel containers in the Schedule hereto for inclusion in any LPG automotive fuel system installed and operated in accordance with the requirements of Australian/New Zealand Standard AS/NZS 1425, subject to the conditions of approval set out in this notice.
Schedule
| Reference No. | Manufacturer | Country of Origin | Specification | Material | Inspection Authority | Maximum Service Pressure (MPa) | Test Pressure (MPa) |
|---|---|---|---|---|---|---|---|
| AF L03B 050 | STEP | Turkey | AS/NZS 3509 | Carbon steel | Bureau Veritas & Blue LPG Pty Ltd | 2.55 | 3.30 |
Note: These LPG fuel containers are manufactured by STEP in Turkey with Bureau Veritas as the Inspection Authority, and then shipped to Australia where they undergo further testing and stamping by Blue LPG Pty Ltd.
Conditions of Approval
These LPG fuel containers are approved subject to the following conditions:
-
That they are permanently and clearly marked, on a suitable metal plate which is securely attached, with characters not less than 2mm high, displaying the following information:
(a) The specification to which the container was manufactured.
(b) The manufacturerβs name or mark.
(c) The serial number of the container. Alternatively, this can be stamped on to the container valve pad.
(d) The date of the original container inspection and the identification mark of the inspection authority which carried out the inspection.
(e) The date of any periodic container test and the identification mark of the cylinder testing station which carried out the test.
(f) The container test pressure.
(g) The nominal water capacity of the container. -
That the container surface coating be in accordance with the requirements in Australian/New Zealand Standard AS/NZS 3509.
-
That they are provided with valve threads and fittings which provide the following functions:
(a) Filling connection incorporating a non return valve.
(b) Service valve incorporating an excess flow valve.
(c) Contents gauge.
(d) Pressure relief valve.
(e) Automatic fill limiter which prevents the container being filled beyond 85% of the total container capacity.
(f) Valves and fittings must have a service pressure rating of at least that of the container to which they are fitted and must comply with the requirements in section 3 of Australian/New Zealand Standard AS/NZS 1425. -
That they are tested prior to installation, and at periods not exceeding 10 years, in accordance with the requirements of Australian Standard AS 2337.
Signed at Wellington this 28th day of March 2014.
H. C. MATHESON, Principal Engineer Vehicles, NZ Transport Agency.
au2033
WorkSafe New Zealand
Health and Safety in Employment (Pressure Equipment, Cranes, and Passenger Ropeways) Regulations 1999
Notice of Exemption for Equipment
Pursuant to Regulation 6 of the Health and Safety in Employment (Pressure Equipment, Cranes, and Passenger Ropeways) Regulations 1999, I, Richard Steel, Manager, Technical Support Services, in exercise of the powers delegated to me by the Secretary of Labour, give notice of exemption from the requirements of these Regulations for design verification of the following one piece of equipment:
Caterpillar, model 312D, Hydraulic Excavator (serial number 312DHRHL00299), when used as a crane, currently in service in New Zealand as owned (and operated) by A. Cave of Tararua Contract Fencing Limited.
This exemption is subject to the conditions that:
- The above-named equipment is assessed by an equipment inspector employed or engaged by an inspection body with respect to construction, non-destructive testing (as
Next Page →
β¨ LLM interpretation of page content
π Approval of LPG Fuel Containers
π Transport & Communications28 March 2014
LPG fuel containers, approval, vehicle equipment, NZ Transport Agency, AS/NZS 1425
- Hugh Cameron Matheson, Principal Engineer Vehicles, NZ Transport Agency
π· Exemption Notice for Hydraulic Excavator
π· Labour & Employmentexemption, hydraulic excavator, crane, WorkSafe New Zealand, Tararua Contract Fencing Limited
- A. Cave, Owner of exempted equipment
- Richard Steel, Manager, Technical Support Services, WorkSafe New Zealand
NZ Gazette 2014, No 36