4092
NEW ZEALAND GAZETTE, No. 141
17 NOVEMBER 2006
Class C
| SAIDI | SAIFI | CAIDI |
|---|---|---|
| Target 31/03/07 | 60 | 0.85 |
| 31/03/2007 Avg forecast | 60 | 0.85 |
| 31/03/2008 Avg forecast | 57 | 0.75 |
| 31/03/2009 Avg forecast | 56 | 0.72 |
| 31/03/2010 Avg forecast | 55 | 0.69 |
| 31/03/2011 Avg forecast | 55 | 0.69 |
Requirement 21 (3)
- Total number of interruptions, together with a breakdown of that total according to interruption class.
| Interruption Class | Number of Interruptions | |||
|---|---|---|---|---|
| 2006 | 2005 | 2004 | 2003 | |
| MainPower | Planned Shut-Down (Class B) | 201 | 236 | 212 |
| Unplanned Interruption (Class C) | 107 | 58 | 82 | |
| Trans Power | Planned Shut-Down (Class A) | - | 1 | - |
| Unplanned Interruption (Class D) | 3 | 2 | 1 | |
| Generation | Unplanned Interruption (Class E) | - | - | - |
| Generation Other | Unplanned Interruption (Class F) | - | - | - |
| Other | Other Interruptions (Class G) | - | - | - |
| Unplanned Interruption (Class G) | - | - | - | |
| Total | Interruptions | 311 | 297 | 295 |
- The total number of faults per 100 circuit kilometres of prescribed voltage electric line.
| Nominal Voltage | Faults per 100 km Total | |||
|---|---|---|---|---|
| 2006 | 2005 | 2004 | 2003 | |
| 33 kV | 1.30 | 3.24 | 4.00 | 0.35 |
| 11 kV | 3.06 | 1.48 | 2.01 | 3.23 |
| TOTAL | 2.92 | 1.66 | 2.18 | 2.97 |
- The total number of faults per 100 circuit kilometres of Underground prescribed voltage electric line, together with a breakdown of that total according to different nominal line voltages.
| Nominal Voltage | Faults per 100 km Underground | |||
|---|---|---|---|---|
| 2006 | 2005 | 2004 | 2003 | |
| 33 kV | 40.50 | - | - | - |
| 11 kV | 4.01 | 3.09 | 1.45 | - |
| TOTAL | 4.60 | 3.03 | 1.42 | - |
- The total number of faults per 100 circuit kilometres of Overhead prescribed voltage electric line, together with a breakdown of that total according to different nominal line voltages.
| Nominal Voltage | Faults per 100 km Overhead | |||
|---|---|---|---|---|
| 2006 | 2005 | 2004 | 2003 | |
| 33 kV | 0.98 | 3.27 | 4.03 | 0.35 |
| 11 kV | 3.03 | 1.44 | 2.03 | 3.34 |
| TOTAL | 2.85 | 1.60 | 2.19 | 3.06 |
- The SAIDI for the total of interruptions:
109.1754 115.5685 99.64 284.35
- The SAIDI for the total number of interruptions within each interruption class:
| Network or Generation Owner | Classification | Minutes per Connected Customer | |||
|---|---|---|---|---|---|
| 2006 | 2005 | 2004 | 2003 | ||
| MainPower | Planned Shut-Down (Class B) | 33.3056 | 49.7782 | 48.59 | 60.83 |
| Unplanned Interruption (Class C) | 69.8694 | 49.5696 | 45.44 | 77.87 | |
| Trans Power | Planned Shut-Down (Class A) | - | 13.2698 | - | 74.38 |
| Unplanned Interruption (Class D) | 6.0004 | 2.9509 | 6.12 | 71.27 | |
| Generation | Unplanned Interruption (Class E) | - | - | - | - |
| Generation Other | Unplanned Interruption (Class F) | - | - | - | - |
| Other | Other Interruptions (Class G) | - | - | - | - |
| Unplanned Interruption (Class G) | - | - | - | - |
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2006, No 141
Gazette.govt.nz —
NZ Gazette 2006, No 141
β¨ LLM interpretation of page content
π
Disclosure of Reliability Performance Measures
(continued from previous page)
π Trade, Customs & IndustryElectricity, Reliability, Interruptions, Performance Measures, Commerce Act, Disclosure Requirements