NEW ZEALAND GAZETTE, No. 141
17 NOVEMBER 2006
MAINPOWER NEW ZEALAND LTD
DISCLOSURE OF RELIABILITY PERFORMANCE MEASURES
PURSUANT TO THE COMMERCE ACT (ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS) NOTICE 2004, REQUIREMENT 21, PART 4.
Disclosure for Statistics Year Ending 31/03/2006
Requirement 21(1)
- Total number of interruptions, together with a breakdown of that total according to interruption class
| NETWORK OR GENERATION OWNER | Disc Reg Class | CLASSIFICATION OF INTERRUPTIONS | |
|---|---|---|---|
| MainPower | B | Planned Shut-downs | 201 |
| C + G | Unplanned Interruptions | 107 | |
| Subtotal | 308 | ||
| Trans Power | A | Planned Shut-downs | 0 |
| D | Unplanned Interruptions | 3 | |
| Subtotal | 3 | ||
| Other | G | Other Interruptions | |
| Other | E | Unplanned Interruptions | |
| Subtotal | |||
| TOTAL | 311 |
-
Interruption targets for the following financial year for-
(a) Planned interruptions by the line owner (Class B); and
(b) Unplanned interruptions originating within the works of the line owner (Class C). -
Average interruption targets for the following financial year and the subsequent 4 financial years for each of-
(a) Planned interruptions by the line owner (Class B); and
(b) Unplanned interruptions originating within the works of the line owner (Class C).
| Target 31/03/07 | Class B Interruptions | Class C Interruptions |
|---|---|---|
| 31/03/2007 Avg forecast | 185 | 80 |
| 31/03/2008 Avg forecast | 175 | 75 |
| 31/03/2009 Avg forecast | 170 | 70 |
| 31/03/2010 Avg forecast | 165 | 70 |
| 31/03/2011 Avg forecast |
- The proportion {expressed as a percentage} of the total number of Class C interruptions not restored within-
(a) 3 hours; and
(b) 24 hours.
| Not restored within 3 hours- % of Class C | Not restored within 24 hours- % of Class C |
|---|---|
| 10.2% | 0% |
-
With respect to faults per 100 circuit kilometers of prescribed voltage electric line, the following information:
(a) The total number of faults; and
(b) The total number of faults targeted for the following financial year; and
(c) The average total number of faults for that financial year and the subsequent 4 financial years; and
(d) A breakdown of the fault information in accordance with paragraphs (a) to (c) by different nominal line voltages. -
The total number of faults per 100 circuit kilometres of underground prescribed voltage electric line, together with a breakdown of that total according to different nominal line voltages.
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2006, No 141
Gazette.govt.nz —
NZ Gazette 2006, No 141
β¨ LLM interpretation of page content
π
Financial Statements of Manpower New Zealand Ltd
(continued from previous page)
π Trade, Customs & IndustryFinancial Performance Measures, System Fixed Assets, Depreciation, Revaluations, Commerce Act, Electricity Information Disclosure Requirements
π Disclosure of Reliability Performance Measures
π Trade, Customs & IndustryElectricity, Reliability, Interruptions, Performance Measures, Commerce Act, Disclosure Requirements