NEW ZEALAND GAZETTE, No. 147
30 AUGUST 2005
Vector Limited
Electricity Lines Business
Reliability Performance Measures to be Disclosed by Disclosing Entities (Other Than Transpower) (continued)
For the year ended 31 March 2005
SCHEDULE 1 – PART 5 (CONTINUED)
- Faults per 100 circuit kilometres of prescribed voltage electric line
| 2005 | 2004¹ | 2003² | 2002 | |
|---|---|---|---|---|
| (a) The total number of faults | 12.63 | 14.98 | 12.57 | 9.36 |
2006
|(b) The total number of targeted faults | | | | 10.75 |
2006-2010
|(c) The average total number of faults | | | | 9.68 |
(d) Breakdown of (a) to (c) according to line voltage
| 6.6kV | 11kV | 22kV | 33kV | 110kV | Total | |
|---|---|---|---|---|---|---|
| (a) 2005 | - | 13.19 | 3.43 | 10.15 | 4.92 | 12.63 |
| (b) 2006 | - | 11.35 | 3.30 | 7.59 | - | 10.75 |
| (c) 2006-2010 | - | 10.21 | 3.05 | 6.72 | - | 9.68 |
- Number of faults per 100 circuit kilometres of underground prescribed voltage electric line
| 6.6kV | 11kV | 22kV | 33kV | 110kV | Total | |
|---|---|---|---|---|---|---|
| 2005 | - | 4.11 | 3.51 | 3.51 | - | 3.71 |
| 2004¹ | - | 6.57 | 3.91 | 20.31 | 6.77 | 6.37 |
| 2003² | - | 6.51 | 5.67 | 0.56 | 1.44 | 5.69 |
| 2002 | - | 7.90 | 2.43 | 4.68 | 6.17 | 7.06 |
- Number of faults per 100 circuit kilometres of overhead prescribed voltage electric line
| 6.6kV | 11kV | 22kV | 33kV | 110kV | Total | |
|---|---|---|---|---|---|---|
| 2005 | - | 21.29 | - | 20.02 | 1.14 | 21.04 |
| 2004¹ | - | 23.26 | - | 21.54 | 0.62 | 22.89 |
| 2003² | 15.15 | 20.28 | - | 7.94 | 7.23 | 19.12 |
| 2002 | 3.76 | 14.15 | - | 8.77 | 23.73 | 14.09 |
¹ Improved information has resulted in Vector reviewing its system lengths for 2004. As a result, the system length and the relevant performance measures and statistics have been restated.
² The 2003 performance statistics have been calculated using a time-weighted average in accordance with the Electricity (Information Disclosure) Regulations 2000, Regulation 33. Vector Limited was combined with UnitedNetworks Limited in October 2002. One month (October 2002) includes the Eastern region of UnitedNetworks Limited as well as the Northern and Wellington regions. The final 5 months are for Vector Limited, plus the Northern and Wellington regions of UnitedNetworks Limited.
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2005, No 147
Gazette.govt.nz —
NZ Gazette 2005, No 147
✨ LLM interpretation of page content
🏭
Vector Limited's Reliability Performance Measures
(continued from previous page)
🏭 Trade, Customs & IndustryElectricity, Reliability, Performance Measures, Faults, Vector Limited