Civil Aviation and Electricity Governance Notices




2590 NEW ZEALAND GAZETTE, No. 108 14 JULY 2005

● The Motunui restricted area (NZR 302) is disestablished.
● The following low flying zones are disestablished – NZL 362 (Pouiatoa), NZL 761 (Hokitika River), NZL 762
(Virgin Flat), NZL 860 (Upper Waimakariri).
● The following low flying zone is amended (new code in brackets) – NZL 367 (South Foxton, NZL 366).
● The Auckland City mandatory broadcast zone (NZB 178) is amended and a code change to NZB 169.
● A new mandatory broadcast zone is established – NZB 269 (Mercer).
● The following general aviation area is disestablished – NZG 956 (Ida).
● The following general aviation areas are amended – NZG 957 (Omarama), NZG 958 (Two Thumbs).
● The following general aviation areas are established – NZG 954 (Ranfurly), NZG 955 (Waitaki), NZG 959 (Rangitata
River).
● The following visual reporting points are established: Red Hill, River Mouth.

Prescribed pursuant to Part 71 of the Civil Aviation Rules, under a delegated authority issued by the Director of Civil Aviation.
Copies of this amendment are available for viewing at http://www.caa.govt.nz (NZ Air Navigation Register) and at Aviation
House, 10 Hutt Road, Lower Hutt, or on application to the Aeronautical Service Unit, CAA, P.O. Box 31-441, Lower Hutt 6315.

Dated this 7th day of July 2005.

LEONARD CHARLES WICKS.
au4421

Electricity Commission

Electricity Act 1992

Notice of Making of a Recommendation and Assessment Concerning the Electricity Governance Rules 2003 – Rule Amendment Proposal No. 72

This notice of a recommendation and assessment concerning the Electricity Governance Rules (“Rules”), Rule Amendment Proposal No. 72, is issued by the Electricity Commission (“Commission”), established under the Electricity Act 1992 (“Act”), pursuant to section 172E (2) (c) of that Act.

Section 172E (2) (c) provides that, no later than 10 working days after making a recommendation concerning the Rules to the Minister of Energy, the Commission must publicise the recommendation and the assessment completed under section 172F of the Act.

Recommendation

On 7 July 2005, the Commission made a recommendation that the existing Schedule C4 of Part C of the Rules, which contains the policy statement, be replaced in its entirety with a new Schedule C4.

Recommended Amendment to the Rules

The key changes from the existing Schedule C4 recommended by the Commission are set out below:

(a) Changes to system operator notifications in the following areas:

(i) system operator required to advise participants if it identifies any new credible events that may result in cascade failure;

(ii) system operator required to advise participants if new environmental or system conditions advised to system operator lead the system operator to believe the loss of a double circuit transmission line could be a contingent risk;

(iii) firmer commitments by system operator to publish details of new permanent and temporary constraints;

(iv) limiting system operator’s obligation to notify participants of changes in temporary constraints to those that the system operator believes will assist it to meet the principal performance objectives;

(v) new requirement for system operator to correctly apply constraints to SPD model; and

(vi) system operator required to advise participants if it identifies new techniques to address conflicts of interest.

(b) Requirement that the system operator maintains voltage stability during and following a contingent event or extended contingent event.

(c) Changes to the system operator’s requirements to schedule sufficient reserve where there is insufficient generation offers and/or reserve offers. Under these circumstances, instead of reducing the reserve requirements, the system operator will:

(i) zero the reserve requirement for a contingent event; and

(ii) reduce demand for an extended contingent event.

(d) Removal of the explicit margins added by the system operator to reserve requirements. These provisions have been replaced by an open provision for the system operator to add an adjustment factor based on its knowledge of the power system.

(e) New requirement for system operator to notify an asset owner if it has provided incomplete or unreliable asset capability information.

(f) Changes to demand step-change limits by purchasers. Limits are now expressed as ramping limits (40 MW per minute with no more than 75 MW in any five-minute period). The system operator must now advise the process by which a purchaser can agree a greater limit and publish existing and new agreements. The provision for system operator to change the step-change demand limits during the term of the policy statement has been removed.

(g) Allowance for the system operator to use any other measures that may mitigate the need to shed demand to manage events greater than those provided for by risk management policies.

(h) Rationalisation and clarification of the demand shedding policy.

(i) Provision for dynamic load distribution factors to be used in the dispatch schedule once the system operator has implemented the software changes required.

(j) Removal of system operator reporting requirements to market administrator and board, which restate requirements set out elsewhere in the Rules.

(k) Removal of provisions for system operator to investigate or support an investigation into an asset owners’ non-compliance with the Rules, which restate requirements set out elsewhere in the Rules.



Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2005, No 108


Gazette.govt.nz PDF NZ Gazette 2005, No 108





✨ LLM interpretation of page content

🚂 Designation and Classification of Airspace (continued from previous page)

🚂 Transport & Communications
7 July 2005
Airspace, Civil Aviation, Control zones, Danger areas, Low flying zones
  • LEONARD CHARLES WICKS

🏭 Electricity Governance Rules Amendment Proposal

🏭 Trade, Customs & Industry
7 July 2005
Electricity Governance Rules, System Operator, Reserve Requirements, Demand Shedding, Voltage Stability
  • Electricity Commission