β¨ Reliability Performance Measures
REGULATION 22
RELIABILITY PERFORMANCE MEASURES
YEAR ENDED 31 MARCH 2003
Interruptions
| 2004/8 Target | 2004 Target | 2003 | 2002 | 2001 | 2000 | |
|---|---|---|---|---|---|---|
| Total Interruptions | 583 | 476 | 553 | 494 | ||
| a) Planned Interruptions (Class B) | 290 | 300 | 324 | 281 | 360 | 342 |
| b) Unplanned interruptions (Class C) | 145 | 240 | 259 | 195 | 193 | 152 |
| Unplanned Interruptions not restored within: | ||||||
| a) 3 Hours (%) | 3.68% | 29.70% | 15.50% | 13.15% | ||
| b) 24 Hours (%) | 0.03% | 1.00% | 7.00% | NIL |
Faults
| 2004/8 Target | 2004 Target | 2003 | 2002 | 2001 | 2000 | |
|---|---|---|---|---|---|---|
| Faults/100km | ||||||
| a) Total No. of faults | 7.50 | 8.00 | 8.96 | 7.51 | 7.50 | 5.98 |
| i) 33kV Line Voltage | ||||||
| a) Total no. of faults | 2.00 | 3.00 | 3.58 | 2.57 | 6.96 | 1.90 |
| ii) 11kV Line Voltage | ||||||
| a) Total no. of faults | 7.6 | 8 | 8.89 | 7.91 | 7.48 | 6.45 |
| Faults/100km of Underground Line |
| a) Total | | | 10.06 | 11.65 | 10.60 | 14.56 |
| b) 33kV | 10.06 | | | 10.87 | | 15.27 |
| c) 11kV | | | 10.06 | 11.46 |
| Faults/100km of Overhead Line |
| a) Total | | 12.52 | 6.73 | 7.10 | 4.55 |
| b) 33kV | 3.20 | 2.82 | 7.70 | | 2.03 |
| c) 11kV | | 9.31 | 7.21 | 6.90 | 4.87 |
RELIABILITY MEASURES
| 2004/8 Target | 2004 Target | 2003 | 2002 | 2001 | 2000 | |
|---|---|---|---|---|---|---|
| TOTAL SAIDI OVERALL | 96.61 | 101.63 | 385.03 | 103.99 | ||
| SAIDI | ||||||
| a) Planned Interruptions (Class B) | 29 | 31 | 24.52 | 31.60 | 62.68 | 56.60 |
| b) Unplanned Interruptions (Class C) | 86 | 94 | 72.08 | 69.10 | 81.27 | 47.30 |
| TOTAL SAIFI OVERALL | 2.02 | 2.14 | 4.75 | 1.48 | ||
| SAIFI | ||||||
| a) Planned Interruptions (Class B) | 0.5 | 0.6 | 0.22 | 0.25 | 0.41 | 0.41 |
| b) Unplanned Interruptions (Class C) | 1.81 | 1.9 | 1.80 | 1.89 | 2.34 | 1.06 |
| b) Unplanned Interruptions TransPower (Class D) | 0.39 | 2.00 |
| Total CAIDI OVERALL | | | 66.6 | 47.49 | 81.06 | 70.3 |
| CAIDI |
| a) Planned Interruptions (Class B) | 58 | 52 | 172.33| 126.6 | 143 | 136.7 |
| b) Unplanned Interruptions (Class C) | 48 | 49 | 56.25 | 36.56 | 34.8 | 44.5 |
| b) Unplanned Interruptions TransPower (Class D) | | 49 | 2.23 | | 123 |
Note: Reliability measures above are calculated on a time weighted basis to reflect the the acquisition of Taupo and Rotorua Networks from United Networks on 1 November 2002. All performance targets for 2004 onwards reflect the ownership of the assets for a twelve month period.
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2003, No 122
Gazette.govt.nz —
NZ Gazette 2003, No 122
β¨ LLM interpretation of page content
π
Unison Networks Limited Reliability Performance Measures
(continued from previous page)
π Trade, Customs & IndustryReliability Measures, Interruptions, Faults, SAIDI, SAIFI, CAIDI, Electricity Regulation