β¨ Financial Performance Measures
Network Waitaki Limited (Lines)
Reliability and Performance Measures
Interruptions
| Class | 2003/07 (Target) | 2003 (Target) | 2002 | 2001 | 2000 | 1999 | |
|---|---|---|---|---|---|---|---|
| Number of interruptions | |||||||
| Planned Interruptions | Class A | 0 | 0 | 0 | 0 | 0 | 0 |
| Class B | 24 | 24 | 70 | 28 | 9 | 8 | |
| Unplanned Interruptions | Class C | 80 | 80 | 75 | 79 | 49 | 76 |
| Class D | 0 | 0 | 0 | 0 | 0 | 0 | |
| Class E-I | 0 | 0 | 0 | 0 | 0 | 0 | |
| Total | 104 | 104 | 145 | 107 | 58 | 84 |
| Proportion Of Total Class C Interruptions not restored: |
|---|
| Within 3 Hours |
| Within 24 Hours |
Faults
| Voltage | 2003/07 (Target) | 2003 (Target) | 2002 | 2001 | 2000 | 1999 |
|---|---|---|---|---|---|---|
| Overall System | ||||||
| Faults per 100 circuit kilometres of prescribed voltage electric line | ||||||
| 0.84 | 0.84 | 4.43 | 4.70 | 2.92 | 4.56 | |
| 33kV | 0.72 | 0.72 | 0.72 | 0.72 | 0.00 | |
| 11kV | 0.85 | 0.85 | 4.76 | 5.05 | 3.19 |
| Overhead |
| Faults per 100 circuit kilometres of prescribed voltage electric line |
| | 4.46 | 4.78 | 2.90 | 4.49 |
| | 33kV | 0.73 | 0.73 | 0.00 | 0.73 |
| | 11kV | 4.79 | 5.15 | 3.16 | 4.83 |
| Underground |
| Faults per 100 circuit kilometres of prescribed voltage electric line |
| | 3.14 | 0.00 | 5.06 | 10.16 |
| | 33kV | 0.00 | 0.00 | 0.00 | 0.00 |
| | 11kV | 3.17 | 0.00 | 5.13 | 10.31 |
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2002, No 106
Gazette.govt.nz —
NZ Gazette 2002, No 106
β¨ LLM interpretation of page content
π°
Financial Performance Measures for Network Waitaki Limited
(continued from previous page)
π° Finance & RevenueFinancial Performance, Efficiency Measures, Network Waitaki Limited, Electricity, Load Factor, Loss Ratio, Capacity Utilisation