β¨ Electricity Reliability Performance Measures
3160 NEW ZEALAND GAZETTE No. 124
DISCLOSURE OF RELIABILITY PERFORMANCE MEASURES UNDER REGULATION 22
OF THE ELECTRICITY (INFORMATION DISCLOSURE) REGULATIONS 1999
Continued
| 2000 | 1999 | 1998 | 1997 |
|---|
11. SAIFI For Total No. of Interruptions within each Interruption Class
Class A - Planned - by Transpower | 20.55 | 0 | 0 | 19.28 |
Class B - Planned - by Line Owners | 31.73 | 58.22 | 115.36| 81.95 |
Class C - Unplanned - by Line Owners | 77.24 | 158.48| 125.16| 205.95|
Class D - Unplanned - by Transpower | 1.69 | 71.55 | 0 | 71.67 |
Class E - Unplanned - by ECNZ | 0 | 0 | 0 | 0 |
Class F - Unplanned - by other generation| 0 | 0 | 0 | 0 |
Class G - any other loss of supply | 0 | 0 | 0 | 0 |
12. SAIFI for the Total No. of Interruptions
| | 2.38 | 6.04 | 4.03 | 7.66 |
13. SAIFI Targets for 2000/01
Class B - Planned - by Line Owners | 0.4 |
Class C - Unplanned - by Line Owners| 2.8 |
14. Av. SAIFI target for 2000/01 and 2004/05 Yrs
Class B - Planned - by Line Owners | 0.3 |
Class C - Unplanned - by Line Owners| 2.5 |
15. SAIFI for the Total No. of Interruptions within Each Interruption Class
Class A - Planned - by Transpower | 0.07 | 0 | 0 | 0.07 |
Class B - Planned - by Line Owners | 0.23 | 0.46 | 0.97 | 0.71 |
Class C - Unplanned - by Line Owners| 1.85 | 4.28 | 3.06 | 4.58 |
Class D - Unplanned - by Transpower| 0.24 | 1.30 | 0 | 2.30 |
Class E - Unplanned - by ECNZ | 0 | 0 | 0 | 0 |
Class F - Unplanned - By Other Generation | 0 | 0 | 0 | 0 |
Class G - Any Other Loss of Supply | 0 | 0 | 0 | 0 |
16. CAIDI for the Total No. of Interruptions
| | 55.1 | 47.7 | 59.7 | 49.6 |
17. CAIDI Targets for 2000/01
Class B - Planned - by Line Owners | 125 | 125 |
Class C - Unplanned - by Line Owners| 40 | 40 |
18. Av. CAIDI Target for 2000/1 to 2004/5 Yrs
Class B - Planned - by Line Owners | 125 |
Class C - Unplanned - by Line Owners| 39 |
19. CAIDI for the Total No. of Interruptions within each Interruption Class
Class A - Planned - by Transpower | 283.0 | 0 | 0 | 300.0 |
Class B - Planned - by Line Owners | 139.0 | 126.8 | 119.0 | 115.7 |
Class C - Unplanned - by Line Owners| 41.8 | 37.0 | 40.9 | 45.0 |
Class D - Unplanned - by Transpower| 7.2 | 55.1 | 0 | 31.1 |
Class E - Unplanned - by ECNZ | 0 | 0 | 0 | 0 |
Class F - Unplanned - By Other Generation | 0 | 0 | 0 | 0 |
Class G - Any Other Loss of Supply | 0 | 0 | 0 | 0 |
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2000, No 124
Gazette.govt.nz —
NZ Gazette 2000, No 124
β¨ LLM interpretation of page content
πΎ
Disclosure of Reliability Performance Measures Under Regulation 22 of the Electricity (Information Disclosure) Regulations 1999
(continued from previous page)
πΎ Primary Industries & ResourcesElectricity, Reliability Performance, Interruptions, Faults, SAIFI, SAIDI, CAIDI, Transpower, Line Owners, ECNZ, Generation, Supply Loss