Centralines Limited – Line Business

13. SAIFI Targets for 2000/01

2000/01
Planned Interruptions 0.60
Unplanned Interruptions 3.30
Total Interruptions 3.90

14. SAIFI Future Targets (Average for the next 5 years)

2000/05
Planned Interruptions 0.55
Unplanned Interruptions 3.12
Total Interruptions 3.67

15. SAIFI per Interruption Class

Interruption Class 1999/00 1998/9 1997/8 1996/7
Planned Transpower 2.00 1.00 0.00 1.00
Planned Centralines 0.70 0.55 0.11 0.17
Unplanned Centralines 4.24 2.18 0.80 1.36
Unplanned Transpower 0 0 1.00 0
Unplanned Centralines Generation 0 0 0 0
Unplanned Other Generators 0 0 0 0
Unplanned Other Line Owner 0 0 0 0
Planned Other Line Owner 0 NA NA NA
Other Interruptions 0 NA NA NA

16. Consumer Average Interruption Duration Index (CAIDI)

1999/00 1998/9 1997/8 1996/7
Total Interruptions 109 132 71.6 158


Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2000, No 103


Gazette.govt.nz PDF NZ Gazette 2000, No 103





✨ LLM interpretation of page content

πŸ’° Centralines Limited – Line Business Reliability Performance Measures (continued from previous page)

πŸ’° Finance & Revenue
Electricity, Performance Measures, Statistics, Centralines Limited, Reliability, Interruptions, SAIFI, CAIDI