2184 NEW ZEALAND GAZETTE No. 80

DUNEDIN ELECTRICITY LTD

ENERGY EFFICIENCY PERFORMANCE MEASURES AND STATISTICS

PURSUANT TO REGULATION 15

ELECTRICITY (INFORMATION DISCLOSURE) REGULATIONS 1994

(1) ENERGY DELIVERY EFFICIENCY PERFORMANCE MEASURES

(a) Load Factor 52.7%
Percentage of electrical energy entering the transmission system
over maximum demand times hours per year.

(b) Loss Ratio 5.92%
Transmission losses over energy entering the system.

(c) Capacity Utilisation 39.78%
Maximum demand over total transformer capacity

(2) STATISTICS

System length, broken by voltage.

                      Total        Overhead       Underground

600V DC 4.10 km 0.90 km 3.2 km
400V 722.98 km 627.89 km 95.09 km
6.6 kV 711.38 km 483.76 km 227.62 km
11 kV 254.75 km 234.80 km 19.95 km
33 kV 225.10 km 149.90 km 75.20 km


Total 1,918.31 km 1,497.25 km 421.06 km

Distribution transformer capacity 467,430 kVA
Maximum demand 185,950 kW
Total electricity supplied from system 807,998,100 kWh
Total electricity conveyed for unrelated parties 125,635,160 kWh
Total network connections 49 390

10



Next Page →

PDF embedding disabled (Crown copyright)

View this page online at:


VUW Te Waharoa PDF NZ Gazette 1995, No 80


NZLII PDF NZ Gazette 1995, No 80





✨ LLM interpretation of page content

🏭 Dunedin Electricity Ltd Energy Efficiency Performance Measures and Statistics (continued from previous page)

🏭 Trade, Customs & Industry
15 August 1995
Energy Efficiency, Performance Measures, Statistics, Electricity, Dunedin Electricity Ltd