NEW ZEALAND GAZETTE
11 AUGUST
TAUPO ELECTRICITY LIMITED
Performance Measures And Statistics (cont)
(e) Maximum demand (in kilowatts).
45,924
(f) Total electricity supplied from the system (in kilowatt hours).
257,592,349
(g) Total amount of electricity (in kilowatt hours) conveyed on behalf of other persons, that are electricity retailers or generators, not in a prescribed business relationship with Taupo Electricity Limited.
1,641,233
(h) Total customers (average).
11,811
5. RELIABILITY PERFORMANCE MEASURES
Reliability Performance Measures pursuant to Regulation 16 and Part IV of the First Schedule of the Electricity (Information Disclosure) Regulations 1994 are:
Interruptions
(a) Total number of interruptions, together with a breakdown of that total according to class:
-
Class A: Planned Trans Power interruption
-
Class B: Planned interruption by any Line Operator (other than Trans Power)
74
-
Class C: Unplanned interruption originating within the principal Line Owner’s works.
99
-
Class D: Unplanned Trans Power interruption
2
-
Class E: Unplanned ECNZ interruption
-
Class F: Unplanned interruption originating from a Generator other than ECNZ
-
Class G: Other
Total Interruptions
175
Faults
(b) Total number of faults per 100 circuit kilometres of prescribed voltage electric lines
| 11 kV | 33 kV | Total | |
|---|---|---|---|
| 10.26 | 5.83 | 9.63 |
(c) Number of faults per 100 circuit kilometres of prescribed voltage overhead lines
| 11 kV | 33 kV | Total | |
|---|---|---|---|
| 10.55 | 6.00 | 9.87 |
(d) Number of faults per 100 circuit kilometres of prescribed voltage underground cables
| 11 kV | 33 kV | Total | |
|---|---|---|---|
| 6.64 | 0.00 | 6.22 |
SAIDI (System Average Interruption Duration Index)
(e) The SAIDI for the total interruptions
383.00
(f) The SAIDI for the total interruptions within each interruption class:
-
Class A: Planned Trans Power interruption
-
Class B: Planned interruption by any Line Operator (other than Trans Power)
50.00
-
Class C: Unplanned interruption originating within the principal Line Owner’s works.
63.00
-
Class D: Unplanned Trans Power interruption
270.00
-
Class E: Unplanned ECNZ interruption
-
Class F: Unplanned interruption originating from a generator other than ECNZ
-
Class G: Other
Next Page →
PDF embedding disabled (Crown copyright)
View this page online at:
VUW Te Waharoa —
NZ Gazette 1995, No 78
NZLII —
NZ Gazette 1995, No 78
✨ LLM interpretation of page content
🏭
Performance Measures and Statistics for Taupo Electricity Limited
(continued from previous page)
🏭 Trade, Customs & IndustryFinancial Performance, Efficiency Measures, Energy Delivery, Statistics, Electricity