VECTOR LIMITED

ELECTRICITY LINES BUSINESS

RELIABILITY PERFORMANCE MEASURES TO BE DISCLOSED BY DISCLOSING ENTITIES (OTHER THAN TRANSPOWER) (CONTINUED)

FOR THE YEAR ENDED 31 MARCH 2007

SCHEDULE 1 – PART 5 (continued)

CAIDI

  1. The CAIDI for the total of all interruptions
2007 2006 2005 2004
173.32 71.55 66.62 70.05
  1. CAIDI targets for the following financial year
2008
(a) Planned (class B) 125.00
(b) Unplanned (class C) 63.35
  1. Average CAIDI targets
2008-2012
(a) Planned (class B) 125.00
(b) Unplanned (class C) 63.35
  1. The CAIDI for the total number of interruptions within each interruption class
Class 2007 2006 2005 2004
Class A - 273.00 - 499.00
Class B 175.67 150.83 164.25 174.18
Class C 79.24 76.47 70.05 68.40
Class D 202.75 15.03 10.88 40.93
Class E - - - -
Class F - - - -
Class G - - - -
Class H - - - -
Class I - - - -

Description of interruption classes as per The Electricity Information Disclosure Requirements 2004

  • Class A: Planned interruption by Transpower
  • Class B: Planned interruption by the principal
  • Class C: An unplanned interruption originating within the principal disclosing entity, where those works are used for carrying out lines business activities
  • Class D: An unplanned interruption originating within the works of Transpower, where those works are used for carrying out line business activities
  • Class E: An unplanned interruption originating within works used, by the principal disclosing entity, for the generation of electricity
  • Class F: An unplanned interruption originating within works used, by persons other than the principal disclosing entity, for the generation of electricity
  • Class G: An unplanned interruption caused by another disclosing entity
  • Class H: A planned interruption caused by another disclosing entity
  • Class I: An interruption not referred to in classes A to H
  1. The increase is mainly due to a Transpower outage on 12 June 2006 and other extreme events.


Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2008, No 39


Gazette.govt.nz PDF NZ Gazette 2008, No 39





✨ LLM interpretation of page content

🏭 Electricity Reliability Performance Measures for Vector Limited (continued from previous page)

🏭 Trade, Customs & Industry
Electricity, Reliability, Faults, Performance measures, Vector Limited, CAIDI, Interruptions