✨ Electricity Reliability Statistics




1 DECEMBER 2006
NEW ZEALAND GAZETTE, No. 161
4701

OTAGONET JOINT VENTURE LINES BUSINESS
RELIABILITY PERFORMANCE MEASURES

PURSUANT TO REQUIREMENT 21 OF THE ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS 2004, SCHEDULE 1 PART 5

Reliability Statistics For Years Ending 31 March 2003, 2004, 2005 and 2006

Class A B C D E F G H I TOTAL
2002/03 - 107 171 1 - - - - - 279
Interruptions 2 115 197 1 - - - - - 315
2003/04 - - - - - - - -
2 153 131 2 - - - - - 288
2004/05 - - - - - -
- 295 188 4 - - - - - 487
2005/06
Predicted 2006/2007
300 190
5-Year Average Target
290 180

| SAIDI |
| 2002/03 | - | 54.0 | 161.8| 9.1 |
| | 45.2 | 395.4| 4.3 | - | - | - | - | - | - | 503.9 |
| 2003/04 | 0.7 | 75.8 | 98.0 | 19.6|
| | - | - | - | - |
| 2004/05 |
| | - | 174.1| 133.0| 6.1 | - | - | - | - | - | 313.2 |
| 2005/06 |
| Predicted 2006/2007 |
| | 215.0 | 140.0|
| 5-Year Average Target |
| | 202.0 | 137.4|

| SAIFI |
| 2002/03 | - | 0.29 | 2.33 | 0.16| - | - | - | - | - | 2.78 |
| 2003/04 | 0.23 | 0.29 | 2.87 | 0.10| - | - | - | - | - | 3.49 |
| 2004/05 | - | 0.45 | 1.27 | 0.40| - | - | - |
| 2005/06 | - | 0.76 | 1.99 | 1.22| - | - | - | - | - | 3.97 |
| Predicted 2006/2007 |
| | 0.95 | 1.90 |
| 5-Year Average Target |
| | 0.91 | 1.86 |

| CAIDI |
| 2002/03 | - | 186.3| 69.5 | 56.6| - | - | - | - | - | 80.9 |
| 2003/04 | 196.5 | 203.6| 137.8| 42.6| - | - | - | - | - | 144.4 |
| 2004/05 | - | 168.4| 77.2 | 49.0| - | - | - |
| 2005/06 | - | 228.8| 67.1 | 5.0 |
| Predicted 2006/2007 |
| | 226.32| 73.68|
| 5-Year Average Target |
| | 221.98| 73.87|

Faults by Voltage

66kV 33kV 11kV Total
2002/03 - 1.32 5.15 4.52
O/H per 100km
2003/04 1.35 1.66 5.83 5.16
2004/05 - 0.72 3.97 3.43
2005/06 - 2.00 5.10 4.55

| UG pzr 100km |
| 2002/03 | - | - | - |
| 2003/04 | - | - | - | - |
| 2004/05 | - | - | - |
| 2005/06 | - | 10.83| 8.73 |

| Total per 100km |
| 2002/03 | - | 1.32 | 5.14 | 4.51 |
| 2003/04 | 1.35 | 1.66 | 5.82 | 5.15 |
| 2004/05 | - | 0.72 | 3.96 | 3.42 |
| 2005/06 | - | 2.00 | 5.11 | 4.56 |
| Predicted 2006/2007 |
| | 0.41 | 1.27 | 4.49 | 3.95 |
| 5-Year Average Target |
| | 0.37 | 1.21 | 4.13 | 3.64 |

  • Class C Interruptions Not Restored in 3 hours: 17.6%
  • Class C Interruptions Not Restored in 24 hours: 0.5%

Reliability Statistics for (three months of 2003 to 30 June 2002) are those achieved by the previous owner, Otago Power Limited.



Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2006, No 161


Gazette.govt.nz PDF NZ Gazette 2006, No 161





✨ LLM interpretation of page content

🏭 OtagoNet Joint Venture Lines Business Reliability Performance Measures (continued from previous page)

🏭 Trade, Customs & Industry
Reliability Statistics, Electricity, SAIDI, SAIFI, CAIDI, Faults, Voltage, Interruptions