β¨ Electricity Reliability Statistics
Reliability Performance Measures (Requirement 21)
SAIFI
| Average SAIFI Targets | SAIFI Targets 2004 | Actual SAIFI 2004 | ||||
|---|---|---|---|---|---|---|
| Class | 2004/08 | 2004 | 2003 | 2002 |
SAIFI for total number of interruptions (= a/b)
where -
a = sum of electricity consumers affected by each of those interruptions
b = Total consumers
| | | | 2.82 | 2.78 | 4.39 | 3.55 |
SAIFI Targets (=a/b)
Planned Interruptions
Class B
| 0.30 | 0.30 |
Unplanned Interruptions
Class C
| 1.70 | 1.70 |
where -
Planned interruptions
a = projected number of electricity consumers affected by each of those interruptions
b = Projected total customers
| 7,463 | 7,463 |
| 24,876 | 24,876 |
Unplanned Interruptions
Class C
a = projected number of electricity consumers affected by each of those interruptions
b = Projected total customers
| 42,289 | 42,289 |
| 24,876 | 24,876 |
SAIFI for total number of interruptions within each interruption class (= a/b)
| Class | |||||
|---|---|---|---|---|---|
| Class A | 0.02 | 0.07 | 0.00 | 0.11 | |
| Class B | 0.20 | 0.39 | 0.29 | 0.41 | |
| Class C | 1.75 | 2.54 | 2.28 | 3.57 | |
| Class D | 0.84 | 0.21 | 0.27 | 0.50 | |
| Class E | 0.00 | 0.00 | 0.00 | 0.00 | |
| Class F | 0.00 | 0.00 | 0.00 | 0.00 | |
| Class G | 0.01 | 0.00 | 0.00 | 0.00 | |
| Class H | 0.00 | 0.00 | 0.00 | 0.00 | |
| Class I | 0.00 | 0.00 | 0.00 | 0.00 |
SAIFI for total of interruptions
where -
a = sum of electricity consumers affected by each of those interruptions within that interruption class
b = Total consumers
| | 2.82 | 2.78 | 4.39 | 3.56 |
| Class | ||||
|---|---|---|---|---|
| Class A | 375 | 1,883 | 2,889 | |
| Class B | 5,026 | 9,765 | 7,478 | 10,849 |
| Class C | 43,485 | 64,049 | 58,173 | 93,310 |
| Class D | 20,791 | 5,000 | 5,430 | 6,955 |
| Class E | 0 | 0 | 0 | 0 |
| Class F | 0 | 0 | 0 | 0 |
| Class G | 180 | 0 | 0 | 0 |
| Class H | 0 | 0 | 0 | 0 |
| Class I | 0 | 0 | 0 | 0 |
b = Total consumers
| 24,876 | 25,254 | 25,552 | 26,128 |
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2005, No 7
Gazette.govt.nz —
NZ Gazette 2005, No 7
β¨ LLM interpretation of page content
ποΈ
Reliability Performance Measures (Requirement 21)
(continued from previous page)
ποΈ Infrastructure & Public WorksElectricity, Reliability, SAIFI, Interruptions, Performance Measures, Statistics