✨ Westpower Limited Performance Measures




21 JANUARY 2005 NEW ZEALAND GAZETTE, No. 25

                                    611

WESTPOWER LIMITED - LINES BUSINESS

2 Efficiency performance measures:

(a) Direct lines costs per kilometre

2004 2003 2002 2001
$ $ $ $
Direct Expenditure 3,325,936 2,441,192 2,558,061 2,199,004
System Length 1,978 1,981 1,971 1,963
Cost per kilometre 1,681.46 1,232.30 1,297.85 1,120.23

(b) Indirect lines costs per electricity Consumer *

2004 2003 2002 2001
$ $ $ $
Indirect Expenditure 1,250,064 1,217,210 1,205,653 898,996
Total consumers * 11,931 12,077 12,072 11,996
Cost per consumer 104.77 100.79 99.87 74.94

*Number of consumers based on ICP connections

Disclosure of energy delivery efficiency performance measures under requirement 20 of the Electricity (Information Disclosure) Requirements 2004 Schedule 1 Part 4.

1 Energy Delivery efficiency performance measures:

(a) Load factor (=a/bc100)

2004 2003 2002 2001
a = kWh of electricity entering system 207,165,465 211,261,285 197,992,332 201,936,757
b = Maximum demand 36,024 38,232 35,650 34,776
c = Total number of hours in year 8,760 8,760 8,760 8,760
Load factor % 65.6% 63.1% 63.4% 66.3%

(b) Loss ratio (=(a/b)*100)

2004 2003 2002 2001
a = losses in electricity in kWh 14,434,000 9,603,837 11,102,063 11,421,041
b = kWh of electricity entering system 207,165,465 211,261,285 197,992,332 201,936,757
Loss ratio % 7.0% 4.5% 5.6% 5.7%

(c) Capacity utilisation (=(a/b)*100)

2004 2003 2002 2001
a = Maximum demand 36,024 38,232 35,650 34,776
b = Transformer Capacity 116,726 109,003 104,363 107,127
Capacity utilisation % 31% 35% 34% 32%

2 Statistics

(a) System Length

Circuit Kilometres 2004 2003 2002 2001
66kV 60 56 47 47
33kV 246 230 230 230
11kV 1,416 1,492 1,492 1,484
230/400V 256 203 202 202
Total 1,978 1,981 1,971 1,963

(b) System Length - Overhead

Circuit Kilometres 2004 2003 2002 2001
66kV 60 56 47 47
33kV 244 230 230 230
11kV 1,383 1,458 1,458 1,452
230/400V 169 142 142 142
Total Overhead 1,856 1,886 1,877 1,871


Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2005, No 25


Gazette.govt.nz PDF NZ Gazette 2005, No 25





✨ LLM interpretation of page content

🏭 Westpower Limited Performance Measures (continued from previous page)

🏭 Trade, Customs & Industry
Financial Performance, Efficiency Measures, Energy Delivery, System Length, Load Factor, Loss Ratio, Capacity Utilisation