✨ Electricity Reliability Performance Measures




THE LINES COMPANY LIMITED - LINE BUSINESS ACTIVITY

8 SAIDI for total of interruptions during :

2005 2004 2003 2002
SAIDI 305.6 400.2 729.0 564.2

9 SAIDI targets for the following year
10 and for the subsequent four financial years

2006 2007 2008 2009 2010 Average 2006/10
Planned (TLC) 117.0 105.6 96.8 96.8 96.8 102.6
Unplanned (TLC) 241.0 221.4 203.2 203.2 203.2 214.4

11 SAIDI according to class

2005 2004 2003 2002
Planned (Transpower) 38.5 7.9 48.9 41.0
Planned (TLC) 79.5 78.2 226.2 199.3
Unplanned (TLC) 146.1 264.4 450.4 265.0
Unplanned (Transpower) 30.0 36.5 3.5 58.9
Generation (Others) 0.0 0.0 0.0 0.0
Other (Private Lines) 11.6 13.2 0.0 0.0

12 SAIFI for total of interruptions during :

2005 2004 2003 2002
SAIFI 4.02 4.96 7.15 6.55

13 SAIFI targets for the following year
14 and for the subsequent four financial years

2006 2007 2008 2009 2010 Average 2006/10
Planned (TLC) 0.6 0.5 0.5 0.5 0.5 0.5
Unplanned (TLC) 3.6 3.5 3.4 3.4 3.4 3.5

15 SAIFI according to class

2005 2004 2003 2002
Planned (Transpower) 0.11 0.38 0.16 0.21
Planned (TLC) 0.43 0.46 1.12 0.95
Unplanned (TLC) 2.52 3.48 5.71 4.44
Unplanned (Transpower) 0.84 0.45 0.15 0.95
Generation (Others) 0.00 0.00 0.00 0.00
Other (Private Lines) 0.12 0.18 0.00 0.00

16 CAIDI for total of interruptions during :

2005 2004 2003 2002
CAIDI 76.1 80.7 102.0 86.1

17 CAIDI targets for the following year
18 and for the subsequent four financial years

2006 2007 2008 2009 2010 Average 2006/10
Planned (TLC) 208.1 195.6 184.4 184.4 184.4 191.4
Unplanned (TLC) 66.2 63.4 60.2 60.2 60.2 62.1

19 CAIDI according to class

2005 2004 2003 2002
Planned (Transpower) 357.0 20.6 300.3 193.1
Planned (TLC) 183.1 169.4 202.5 210.2
Unplanned (TLC) 58.0 76.0 78.8 59.7
Unplanned (Transpower) 33.6 80.5 22.6 62.3
Generation (Others) 0.0 0.0 0.0 0.0
Other (Private Lines) 100.3 72.2 0.0 0.0

24 AUGUST 2005

PUBLISHED BY THE
DEPARTMENT OF INTERNAL AFFAIRS
PRINTED BY WICKLIFFE LIMITED

NEW ZEALAND GAZETTE, No. 139

ISSN 0111-5650
Price $\$5.00 (inc. G.S.T.)




Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2005, No 139


Gazette.govt.nz PDF NZ Gazette 2005, No 139





✨ LLM interpretation of page content

πŸ’° Reliability Performance Measures for The Lines Company Limited (continued from previous page)

πŸ’° Finance & Revenue
24 August 2005
Reliability, Interruptions, Faults, Electricity Distribution, Performance Targets
  • Department of Internal Affairs