THE POWER COMPANY LIMITED LINE BUSINESS

RELIABILITY PERFORMANCE MEASURES

PURSUANT TO REQUIREMENT 21 OF THE ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS 2004, SCHEDULE 1 PART 5

RELIABILITY STATISTICS FOR YEARS ENDING 31 MARCH 2002, 2003, 2004 AND 2005

Class A B C D E F G H I TOTAL
Interruptions
2001/02 - 194 375 - - 1 - - - 570
2002/03 - 149 388 - - 3 - - - 540
2003/04 - 85 391 3 - - - - - 479
2004/05 - 63 354 - - - - - - 417
Predicted 2005/2006 - 206 406 - - - - - -
5-Year Average Target - 214 355 - - - - - -

| SAIDI | | | | | | | | | | |
| 2001/02 | - | 20.0 | 117.8 | - | - | 1.3 | - | - | - | 139.0 |
| 2002/03 | - | 18.9 | 147.8 | - | - | 0.3 | - | - | - | 167.0 |
| 2003/04 | - | 11.1 | 140.8 | 5.4 | - | - | - | - | - | 157.3 |
| 2004/05 | - | 7.7 | 117.8 | - | - | - | - | - | - | 125.5 |
| Predicted 2005/2006 | - | 16.3 | 160.5 | - | - | - | - | - | - | |
| 5-Year Average Target | - | 17.7 | 154.2 | - | - | - | - | - | - | |

| SAIFI | | | | | | | | | | |
| 2001/02 | - | 0.14 | 2.75 | - | - | 0.01| - | - | - | 2.88 |
| 2002/03 | - | 0.11 | 3.22 | - | - | 0.01| - | - | - | 3.33 |
| 2003/04 | - | 0.10 | 3.42 | 0.61| - | - | - | - | - | 4.13 |
| 2004/05 | - | 0.04 | 2.96 | - | - | - | - | - | - | 3.00 |
| Predicted 2005/2006 | - | 0.12 | 3.52 | - | - | - | - | - | - | |
| 5-Year Average Target | - | 0.12 | 3.45 | - | - | - | - | - | - | |

| CAIDI | | | | | | | | | | |
| 2001/02 | - | 146.8| 43.1 | - | - | 161.0| - | - | - | 48.3 |
| 2002/03 | - | 174.4| 45.9 | - | - | 40.3 | - | - | - | 50.1 |
| 2003/04 | - | 111.3| 41.2 | 8.9| - | - | - | - | - | 38.1 |
| 2004/05 | - | 188.3| 39.8 | - | - | - | - | - | - | 41.9 |
| Predicted 2005/2006 | - | 137.5| 45.5 | - | - | - | - | - | - | |
| 5-Year Average Target | - | 143.1| 44.6 | - | - | - | - | - | - | |

Faults by Voltage

66kV 33kV 11kV Total
OH per 100km
2001/02 2.31 1.15 6.27 5.68
2002/03 1.14 2.27 6.65 6.03
2003/04 1.68 3.37 6.03 5.62
2004/05 1.40 2.18 5.06 4.71

| UG per 100km | | | | |
| 2001/02 | - | - | 1.93 | 1.86 |
| 2002/03 | - | - | 3.65 | 3.47 |
| 2003/04 | - | - | - | - |
| 2004/05 | - | 29.07 | 2.22 | 3.20 |

| Total per 100km| | | | |
| 2001/02 | 2.31 | 1.14 | 6.24 | 5.65 |
| 2002/03 | 1.14 | 2.25 | 6.62 | 6.00 |
| 2003/04 | 1.68 | 3.34 | 5.96 | 5.56 |
| 2004/05 | 1.40 | 2.38 | 5.02 | 4.69 |
| Predicted 2005/2006 | 1.58 | 3.17 | 5.77 | 5.41 |
| 5-Year Average Target | 1.55 | 3.10 | 5.65 | 5.30 |

Class C Interruptions Not Restored in

  • 3 hours: 2.82%
  • 24 hours: 0%


Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2005, No 133


Gazette.govt.nz PDF NZ Gazette 2005, No 133





✨ LLM interpretation of page content

πŸ’° Reliability Performance Measures for The Power Company Limited (continued from previous page)

πŸ’° Finance & Revenue
Reliability Statistics, Interruptions, SAIDI, SAIFI, CAIDI, Faults by Voltage, Class C Interruptions