OTAGONET JOINT VENTURE LINES BUSINESS

RELIABILITY PERFORMANCE MEASURES

PURSUANT TO REQUIREMENT 21 OF THE ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS 2004, SCHEDULE 1 PART 5

Reliability Statistics For Years Ending 31 March 2002, 2003, 2004 and 2005

Class A B C D E F G H I TOTAL
2001/02 - 119 178 2 - - - - -
Interruptions 2002/03 - 107 171 1 - - - - -
2003/04 2 115 197 1 - - - - -
2004/05 2 153 131 2 - - - - -
Predicted 2005/2006 140 190
5-Year Average Target 149 184

| SAIDI | 2001/02 | - | 65.5 | 106.4 | 50.7 | - | - | - | - | - | 222.6 |
| | 2002/03 | - | 54.0 | 161.8 | 9.1 | - | - | - | - | - | 224.9 |
| | 2003/04 | 45.2 | 59.0 | 395.4 | 4.3 | - | - | - | - | - | 503.9 |
| | 2004/05 | 0.7 | 75.8 | 98.0 | 19.6 | - | - | - | - | - | 194.1 |
| | Predicted 2005/2006 |
| | 5-Year Average Target | 78.5 | 167.0 |
| | | 83.3 | 157.3 |

| SAIFI | 2001/02 | - | 0.31 | 1.45 | 0.83 | - | - | - | - | - | 2.59 |
| | 2002/03 | - | 0.29 | 2.33 | 0.16 | - | - | - | - | - | 2.78 |
| | 2003/04 | 0.23 | 0.29 | 2.87 | 0.10 | - | - | - | - | - | 3.49 |
| | 2004/05 | - | 0.45 | 1.27 | 0.40 | - | - | - | - | - | 2.12 |
| | Predicted 2005/2006 | | 0.44 | 1.86 |
| | 5-Year Average Target | 0.46 | 1.80 |

| CAIDI | 2001/02 | - | 211.2 | 73.4 | 61.1 | - | - | - | - | - | 85.9 |
| | 2002/03 | - | 186.3 | 69.5 | 56.6 | - | - | - | - | - | 80.9 |
| | 2003/04 | 196.5 | 203.6 | 137.8| 42.6 | - | - | - | - | - | 144.4 |
| | 2004/05 | - | 168.4 | 77.2 | 49.0 | - | - | - | - | - | 91.6 |
| | Predicted 2005/2006 |
| | 5-Year Average Target | 180.0 | 90.0 |
| | | | 87.3 |

Faults by Voltage

66kV 33kV 11kV Total
2001/02 - 1.51 5.29
OH per 100km 2002/03 - 1.32 5.14
2003/04 1.35 1.66 5.82
2004/05 - 0.72 3.96
Predicted 2005/2006
5-Year Average/Target 0.51 1.44 5.63

| UG per 100km| 2001/02 | - | - | - | - |
| | 2002/03 | - | 1.52 | 5.30 | 4.67 |
| | 2003/04 | - | - | - | - |
| | 2004/05 | - | - | - | - |

| Total per 100km | 2001/02 | - | 1.51 | 5.29 | 4.66 |
| | 2002/03 | - | 1.32 | 5.14 | 4.51 |
| | 2003/04 | 1.35 | 1.66 | 5.82 | 5.15 |
| | 2004/05 | - | 0.72 | 3.96 | 3.42 |
| | Predicted 2005/2006 |
| | 5-Year Average/Target | 0.50 | 1.33 | 5.46 | 4.77 |

Class C Interruptions Not Restored in:

  • 3 hours: 6.1%
  • 24 hours: 0.0%

Reliability Statistics for 2002 and three months of 2003 to 30 June 2002 are those achieved by the previous owner, Otago Power Limited.



Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2005, No 128


Gazette.govt.nz PDF NZ Gazette 2005, No 128





✨ LLM interpretation of page content

πŸ—οΈ Otagonet Joint Venture Lines Business Reliability Performance Measures (continued from previous page)

πŸ—οΈ Infrastructure & Public Works
Reliability, Statistics, Interruptions, SAIDI, SAIFI, CAIDI, Faults by Voltage, Performance Measures, Electricity