(2) Pipework to which this clause applies must be designed, constructed, installed, operated, inspected,
tested, and maintained so as to ensure that the pipework is suitable for all reasonably foreseeable
working pressures, temperatures, and structural stresses to which it is likely to be subjected.
(3) Pipework to which this clause applies must comply with the following:
(a) transfer lines must be designed, constructed, and installed in accordance with—
(i) ASME B31.4; or
(ii) AS/NZS 2885.1: 1997; or
(iii) if the transfer lines are part of the underground pipework of an underground petroleum
storage system, section 13 and section 14 of the UPSS; or
(iv) a code of practice approved by the Authority under section 79 of the Act that specifies
requirements equivalent to the requirements specified in subparagraph (i), or
subparagraph (ii), or subparagraph (iii):
(b) transfer lines must be operated, inspected, tested, and maintained in accordance with—
(i) AIP CP26: 1995; or
(ii) AS/NZS 2885.3: 1997; or
(iii) if the transfer lines are part of the underground pipework of an underground petroleum
storage system, section 14 of the UPSS; or
(iv) a code of practice approved by the Authority under section 79 of the Act that specifies
requirements equivalent to the requirements specified in subparagraph (i), or
subparagraph (ii), or subparagraph (iii):
(c) process pipework must be designed, constructed, and installed in accordance with—
(i) ASME B31.3; or
(ii) ASME B31.4; or
(iii) AS/NZS 2885.1: 1997; or
(iv) a code of practice approved by the Authority under section 79 of the Act that specifies
requirements to the requirements specified in subparagraph (i), or subparagraph (ii), or
subparagraph (iii):
(d) process pipework must be operated, inspected, tested, and maintained in accordance with—
(i) API 570; or
(ii) AS/NZS 2885.3: 1997; or
(iii) a code of practice approved by the Authority under section 79 of the Act that specifies
requirements equivalent to the requirements specified in subparagraph (i) or
subparagraph (ii).
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2004, No 35
Gazette.govt.nz —
NZ Gazette 2004, No 35
✨ LLM interpretation of page content
🏥
Amendments to Hazardous Substances Regulations
(continued from previous page)
🏥 Health & Social WelfareRegulations, Hazardous Substances, Pipework, Safety Standards, Design Requirements, Installation Requirements, Maintenance Standards, Inspection Requirements, Testing Requirements, Structural Stress, Working Pressure, Temperature, Transfer Lines, Process Pipework, ASME B31.4, AS/NZS 2885.1, AS/NZS 2885.3, API 570, AIP CP26, UPSS, Authority Approval