TOP ENERGY LIMITED
Performance Measures and Statistics
For the Year Ended 31 March 2004
Regulation 22
Reliability Performance Measures
i. Total number of interruptions and breakdowns by interruption class
| Class Type of Interruption | 5 Yr Average | Target 2005 | 2004 No | 2003 No | 2002 No | 2001 No |
|---|---|---|---|---|---|---|
| A Planned - Transpower | 0 | 2 | 0 | 0 | ||
| B Planned - Top Energy | 155 | 155 | 160 | 144 | 195 | 218 |
| C Unplanned - Top Energy | 190 | 210 | 219 | 249 | 244 | 235 |
| D Unplanned - Transpower | 1 | 0 | 6 | 0 | ||
| E Unplanned - Embedded Generation | 0 | 0 | 0 | 0 | ||
| F Unplanned - Other Generation | 0 | 0 | 0 | 0 | ||
| G Unplanned - Another Line owner | 0 | 0 | 0 | 0 | ||
| H Planned - Another Line owner | 0 | 0 | 0 | 0 | ||
| I Any other interruptions | 3 | 0 | 0 | 0 | ||
| Total - All interruptions | 383 | 395 | 447 | 453 |
Class C interruptions not restored:
- a Within 3 hours: 42% | 30% | % | 34% | 27%
- b Within 24 hours: 1% | 6% | % | 0% | 0%
ii. Number of faults per 100 circuit kms
| Line Voltage | Total | Underground | Overhead |
|---|---|---|---|
| 2004 | 2003 | 2002 | |
| 100kV | |||
| 66kV | |||
| 33kV | 4.78 | 7.74 | 4.10 |
| 11kV | 7.28 | 7.21 | 7.34 |
| 6.6kV | |||
| 3.3kV | |||
| Total | 7.06 | 7.25 | 7.11 |
| Target Faults: |
| 33kV | 5 Yr Average | 2005 Target |
| | 3.7 | 3.7 |
| 11kV | 6.4 | 7.4 |
| Total | 6.1 | 6.8 |
iii. Breakdown of statistics by interruption class
| Class Type of Interruption | SAIDI (Minutes) | SAIFI (Interruptions) | CAIDI (Minutes) |
|---|---|---|---|
| 2004 | 2003 | 2002 | |
| A Planned - Transpower | 0.0 | 0.0 | 148.0 |
| B Planned - Top Energy | 39.5 | 37.0 | 48.0 |
| C Unplanned - Top Energy | 311.9 | 382.0 | 287.0 |
| D Unplanned - Transpower | 1.5 | 0.0 | 191.0 |
| E Unplanned - Embedded Generation | 0.0 | 0.0 | 0.0 |
| F Unplanned - Other Generation | 0.0 | 0.0 | 0.0 |
| G Unplanned - Another Line owner | 0.0 | 0.0 | 0.0 |
| H Planned - Another Line owner | 0.0 | 0.0 | 0.0 |
| I Any other interruption | 0.0 | 0.0 | 0.0 |
| Total - All interruptions | 352.9 | 419.0 | 674.0 |
| Targets: | 5 Yr Average | Target 2005 |
| B Planned - Top Energy | 40 | 40 |
| C Unplanned - Top Energy | 270 | 280 |
| | SAIFI (Interruptions) | CAIDI (Minutes) |
| | 5 Yr Average | Target 2005 |
| | 0.3 | 0.3 |
| C Unplanned - Top Energy | 4.9 | 4.9 |
| | 133 | 133 |
| | 55 | 57 |
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2004, No 173
Gazette.govt.nz —
NZ Gazette 2004, No 173
β¨ LLM interpretation of page content
π
Top Energy Limited Performance Measures and Statistics
(continued from previous page)
π Trade, Customs & IndustryEnergy, Performance Measures, Reliability, Statistics, Faults, Interruptions