WAIPA NETWORKS LIMITED - LINES BUSINESS

2003 2002 2001 2000

Disclosure of reliability performance measures under regulation 22 of the Electricity (Information Disclosure) Regulations 1999 as amended by the Electricity (Information Disclosure) Amendment Regulations 2000.

1 Total number of interruptions

  • Class A - Planned - by Transpower | 0 | 0 | 0 | 0 |
  • Class B - Planned - by Waipa Networks | 122 | 149 | 140 | 223 |
  • Class C - Unplanned - by Waipa Networks| 111 | 103 | 109 | 107 |
  • Class D - Unplanned - by Transpower | 1 | 1 | 1 | 2 |
  • Class E - Unplanned - by Line Owner genera | 0 | 0 | 0 | 0 |
  • Class F - Unplanned - by other generation | 0 | 0 | 0 | 0 |
  • Class G - Unplanned - by another line owner | 3 | 2 | 6 | 0 |
  • Class H - Planned - by another line owner | 0 | 0 | 0 | 0 |
  • Class I - Any other loss of supply | 0 | 0 | 0 | 0 |

Total | 237 | 255 | 256 | 332 |

2 Interruption targets for 2003 / 2004

  • Class B - Planned - by Waipa Networks | 75 |
  • Class C - Unplanned - by Waipa Networks | 103 |

3 Average interruption targets for 2003 / 2004 to 2007 / 2008 years

  • Class B - Planned - by Waipa Networks | 66 |
  • Class C - Unplanned - by Waipa Networks | 98 |

4 Proportion of Class C interruptions not restored within: (=(a/b)*100)

  • 3 Hours

    • a = number of interruptions restored within 3 | 25 | 31 | 20 | 19 |
    • b = Total number of Class C interruptions | 111| 103| 109| 107|
    • Proportion | 23%| 30%| 18%| 18%|
  • 24 Hours

    • a = number of interruptions restored within 24 | 0 | 0 | 0 | 0 |
    • b = Total number of Class C interruptions | 111| 103| 109| 107|
    • Proportion | 0% | 0% | 0% | 0% |

5 (a) The total number of faults per 100 circuit kilometres of prescribed voltage electric line

  • 11kV | 8.37 | 7.78 | 8.30 | 7.91 |

(b) Target for 2003 / 2004 year

  • 11kV | 7.77 |

(c) Average Target for 2003 / 2004 to 2007 / 2008 years

  • 11kV | 7.39 |

6 The total number of faults per 100 circuit kilometres of underground prescribed voltage electric line

  • 11kV | 0.00 | 0.00 | 3.23 | 2.27 |

7 The total number of faults per 100 circuit kilometres of overhead prescribed voltage electric line

  • 11kV | 8.60 | 7.99 | 8.42 | 8.10 |


Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2003, No 79


Gazette.govt.nz PDF NZ Gazette 2003, No 79





✨ LLM interpretation of page content

πŸ’° Disclosure of Reliability Performance Measures for Waipa Networks Limited (continued from previous page)

πŸ’° Finance & Revenue
Reliability Performance Measures, Electricity, Interruptions, Faults, Waipa Networks Limited