β¨ Electricity Reliability Performance Measures
27 JUNE
NEW ZEALAND GAZETTE
1949
8 SAIDI for total of interruptions during :
| 2002 | 2001 | 2000 | 1999 | |
|---|---|---|---|---|
| SAIDI | 564.2 | 573.6 | 472.8 | 588.9 |
9 SAIDI targets for the following year
10 and for the subsequent four financial years
| 2003 | 2004 | 2005 | 2006 | 2007 | Average 2003/07 | |
|---|---|---|---|---|---|---|
| Planned (TLC) | 155.0 | 110.0 | 90.0 | 81.0 | 73.0 | 101.8 |
| Unplanned (TLC) | 230.0 | 210.0 | 180.0 | 162.0 | 146.0 | 185.6 |
11 SAIDI according to class
| 2002 | 2001 | 2000 | 1999 | |
|---|---|---|---|---|
| Planned (Transpower) | 41.0 | 13.3 | 0.0 | 0.0 |
| Planned (TLC) | 199.3 | 207.7 | 203.4 | 239.5 |
| Unplanned (TLC) | 265.0 | 321.2 | 242.4 | 329.7 |
| Unplanned (Transpower) | 58.9 | 28.0 | 27.0 | 19.7 |
| Generation (Others) | 0.0 | 3.4 | 0.0 | 0.0 |
12 SAIFI for total of interruptions during :
| 2002 | 2001 | 2000 | 1999 | |
|---|---|---|---|---|
| SAIFI | 6.55 | 6.51 | 7.34 | 8.88 |
13 SAIFI targets for the following year
14 and for the subsequent four financial years
| 2003 | 2004 | 2005 | 2006 | 2007 | Average 2003/07 | |
|---|---|---|---|---|---|---|
| Planned (TLC) | 0.7 | 0.5 | 0.4 | 0.4 | 0.3 | 0.5 |
| Unplanned (TLC) | 3.8 | 3.2 | 2.6 | 2.3 | 2.1 | 2.8 |
15 SAIFI according to class
| 2002 | 2001 | 2000 | 1999 | |
|---|---|---|---|---|
| Planned (Transpower) | 0.21 | 0.06 | 0.00 | 0.00 |
| Planned (TLC) | 0.95 | 1.12 | 0.91 | 1.25 |
| Unplanned (TLC) | 4.44 | 4.42 | 5.25 | 6.43 |
| Unplanned (Transpower) | 0.95 | 0.78 | 1.18 | 1.20 |
| Generation (Others) | 0.00 | 0.13 | 0.00 | 0.00 |
16 CAIDI for total of interruptions during :
| 2002 | 2001 | 2000 | 1999 | |
|---|---|---|---|---|
| CAIDI | 86.1 | 88.1 | 64.4 | 66.3 |
17 CAIDI targets for the following year
18 and for the subsequent four financial years
| 2003 | 2004 | 2005 | 2006 | 2007 | Average 2003/07 | |
|---|---|---|---|---|---|---|
| Planned (TLC) | 221.4 | 220.0 | 225.0 | 225.0 | 225.0 | 223.3 |
| Unplanned (TLC) | 60.5 | 65.6 | 69.2 | 69.2 | 69.2 | 66.8 |
19 CAIDI according to class
| 2002 | 2001 | 2000 | 1999 | |
|---|---|---|---|---|
| Planned (Transpower) | 193.1 | 240.0 | 0.0 | 0.0 |
| Planned (TLC) | 210.2 | 184.8 | 223.5 | 191.6 |
| Unplanned (TLC) | 59.7 | 72.7 | 46.2 | 51.3 |
| Unplanned (Transpower) | 62.3 | 35.8 | 22.9 | 16.4 |
| Generation (Others) | 0.0 | 25.5 | 0.0 | 0.0 |
LexisNexis
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2003, No 74
Gazette.govt.nz —
NZ Gazette 2003, No 74
β¨ LLM interpretation of page content
ποΈ
Reliability Performance Measures for The Lines Company Limited
(continued from previous page)
ποΈ Infrastructure & Public WorksElectricity, Interruptions, Faults, Performance Measures, The Lines Company Limited