✨ Land Severance and Building Restrictions
8 MAY NEW ZEALAND GAZETTE 1289
(v) In the event of any dispute arising between the
parties in respect of or in connection with this
building restriction, the parties shall, without
prejudice to any other right or entitlement they
may have under this agreement or otherwise:
-
Explore whether the dispute can be resolved
by use of the alternative dispute resolution
technique of mediation. The rules governing
such techniques shall be agreed between the
parties or as recommended by the New Zealand
Law Society or as selected by the Chairman of
the New Zealand Chapter of LEADR (Lawyers
Engaged in Alternative Dispute Resolution); and -
In the event the dispute is not resolved without
28 days of written notice by one party to the
other of the dispute (or such further period
agreed in writing between the parties), either
party may refer the dispute to arbitration under
the provisions of the Arbitration Act 1996 or any
amendment or re-enactment of it. The arbitrator
shall be agreed between the parties within
10 days of written notice of the referral by the
referring party to the other or, failing agreement,
appointed by the President of the New Zealand
Law Society. In either case, the arbitrator shall
not be a person who has participated in any
informal dispute resolution procedure in respect
of the dispute.
(vi) Before any building or structure is erected or
any earthworks are carried out on the fill area, the
owner shall submit plans and specifications in
respect of same in commercial confidence to Transit
New Zealand for its approval, such approval not
to be unreasonably or arbitrarily withheld where:
-
The plans and specifications specifically address
and accommodate any particular engineering
requirements for the land; and -
The proposed building or structure will be
erected and any proposed earthworks will
be carried out on the fill area in line with
the recommendations of a registered engineer
experienced in soil mechanics; and -
Transit New Zealand is reasonably satisfied such
building or structure or such earthworks will not
create any hazard to the motorway or adversely
affect the structural integrity of the motorway.
The Crown shall cause Transit New Zealand to
provide its approval, or reasons for its disapproval, of
the plans and specifications for the proposed building
or structure or the proposed earthworks on the fill area
within two weeks of receipt of the foregoing from the
owner, or such longer time as the parties may agree.
North Auckland Land District—Rodney District
First Schedule
Severance
Area
m2 Being
8248 Part Lot 4, D.P. 142792; shown as “Section 14”
on S.O. Plan 317214 (part Gazette Notice
C. 449703.3).
Second Schedule
Fill Area
Part Lot 4, D.P. 142792; marked “Z” on S.O. Plan 317214
(part Gazette Notice C. 449703.3).
Dated at Auckland this 29th day of April 2003.
R. J. SUTHERLAND, for the Minister for Land Information.
(LINZ CPC/1998/2741)
ln2845
Land Taken as Severance and Building Restriction Created—State Highway No. 1, Albany–Puhoi, Rodney District
Pursuant to the Public Works Act 1981, and to a delegation
from the Minister for Land Information, R. J. Sutherland,
Land Information New Zealand:
(a) Declares the land described in the First Schedule to
this notice to be taken, under section 119 (1), and shall vest
in the Crown on the date of publication hereof in the
New Zealand Gazette.
(b) Pursuant to section 236, declares the land described
in the Second Schedule to this notice (“the fill area”) to be
subject to the following restrictions:
(i) No person shall erect or permit to be erected any
building or structure or carry out any earthworks
on the fill area otherwise than in accordance with
the recommendations of a registered engineer
experienced in soil mechanics.
(ii) Any building or structure erected or any earthworks
carried out on the fill area shall be erected or carried
out at the sole risk of the owner and the owner shall
have no recourse to the Crown in respect of the
fill area.
(iii) The owner will not erect any building or structure or
carry out any earthworks on the fill area in a manner
that will adversely affect the structural integrity of
the motorway, and will not object to any application
by the Crown seeking building or resource consents
required in respect of the use and operation of the
motorway for any reason relating to the effects of
such works or operation on any building or structure
erected on the fill area.
(iv) The covenants contained herein shall be enforceable
only against the owners and occupiers from time to
time of the land.
(v) In the event of any dispute arising between the
parties in respect of or in connection with this
building restriction, the parties shall, without
prejudice to any other right or entitlement they
may have under this agreement or otherwise:
-
Explore whether the dispute can be resolved
by use of the alternative dispute resolution
technique of mediation. The rules governing
such techniques shall be agreed between the
parties or as recommended by the New Zealand
Law Society or as selected by the Chairman of
the New Zealand Chapter of LEADR (Lawyers
Engaged in Alternative Dispute Resolution); and -
In the event the dispute is not resolved without
28 days of written notice by one party to the
other of the dispute (or such further period
agreed in writing between the parties), either
party may refer the dispute to arbitration under
the provisions of the Arbitration Act 1996 or any
amendment or re-enactment of it. The arbitrator
shall be agreed between the parties within
10 days of written notice of the referral by the
referring party to the other or, failing agreement,
appointed by the President of the New Zealand
Law Society. In either case, the arbitrator shall
not be a person who has participated in any
informal dispute resolution procedure in respect
of the dispute.
(vi) Before any building or structure is erected or
any earthworks are carried out on the fill area, the
owner shall submit plans and specifications in
respect of same in commercial confidence to Transit
New Zealand for its approval, such approval not
to be unreasonably or arbitrarily withheld where:
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2003, No 48
Gazette.govt.nz —
NZ Gazette 2003, No 48
✨ LLM interpretation of page content
🏗️
Land Taken as Severance and Building Restriction Created—State Highway No. 1, Albany–Puhoi, Rodney District
(continued from previous page)
🏗️ Infrastructure & Public Works29 April 2003
Public Works Act 1981, Land Severance, Building Restrictions, State Highway, Rodney District
- R. J. Sutherland, for the Minister for Land Information