β¨ Powerco Performance Measures
27 AUGUST
NEW ZEALAND GAZETTE
3147
18.5c Total Number Of Faults Per 100km
Of Prescribed Voltage Line
(Targeted for the Following Financial Year
and Subsequent 4 Financial Years)
| Nominal Voltage | 2004 Powerco Number of Faults/100km | 2005-2008 Powerco Number of Faults/100km |
|---|---|---|
| 110kV | - | - |
| 66kV | 4.95 | 4.86 |
| 33kV | 6.49 | 6.41 |
| 22kV | 9.39 | 9.30 |
| 11kV | 9.21 | 9.13 |
| 6.6kV | 9.60 | 9.62 |
| 3.3kV | - | - |
| Total (Weighted Average) | 8.96 | 8.88 |
18.6 Total Number Of Faults Per 100km Of
Prescribed Voltage Underground Line
| Nominal Voltage | 2003 Powerco Number of Faults/100km | 2002 Powerco Number of Faults/100km | 2001 Powerco Number of Faults/100km | 2000 Powerco Number of Faults/100km |
|---|---|---|---|---|
| 110kV | - | - | - | - |
| 66kV | 0.00 | - | - | - |
| 33kV | 0.58 | - | - | - |
| 22kV | 0.00 | - | - | - |
| 11kV | 4.08 | 4.25 | 3.29 | 4.92 |
| 6.6kV | 0.00 | - | - | - |
| 3.3kV | - | - | - | - |
| Total | 3.78 | 3.83 | 2.94 | 4.47 |
Note: 18.6 The number of faults per km is based on time weighted average data.
18.7 Total Number Of Faults Per 100km Of
Prescribed Voltage Overhead Line
| Nominal Voltage | 2003 Powerco Number of Faults/100km | 2002 Powerco Number of Faults/100km | 2001 Powerco Number of Faults/100km | 2000 Powerco Number of Faults/100km |
|---|---|---|---|---|
| 110kV | - | - | - | - |
| 66kV | 9.32 | 4.17 | 3.59 | - |
| 33kV | 6.80 | 13.04 | 13.27 | 8.83 |
| 22kV | 12.18 | 9.17 | 11.66 | 12.82 |
| 11kV | 12.32 | 6.21 | 5.34 | 0.72 |
| 6.6kV | 4.86 | - | - | - |
| 3.3kV | - | - | - | - |
| Total | 11.56 | 8.64 | 10.67 | 10.62 |
Note: 18.7 The number of faults per km is based on time weighted average data.
18.8 SAIDI
| Interruption Class | 2003 Powerco SAIDI | 2002 Powerco SAIDI | 2001 Powerco SAIDI | 2000 Powerco SAIDI |
|---|---|---|---|---|
| Class A - Transpower Planned | 3.46 | 8.82 | 7.51 | 6.53 |
| Class B - Distributor Planned | 46.99 | 38.02 | 23.59 | 13.23 |
| Class C - Distributor Unplanned | 234.35 | 91.92 | 60.84 | 89.73 |
| Class D - Transpower Unplanned | 10.37 | 20.59 | 3.75 | 1.05 |
| Class E - ECNZ Unplanned | 0.00 | - | - | - |
| Class F - Other Generator Unplanned | 0.16 | 0.23 | - | - |
| Class H - Other Owner | - | - | - | - |
| Class I - Other Owner ( Not in A - I) | - | - | - | - |
| Total | 296.65 | 159.57 | 95.69 | 109.53 |
Note: 18.8 SAIDI, SAIFI and CAIDI are calculated using time weighted averages for all factors. ie: using total Western plus 5/12 Eastern customer minutes, customer interruptions, and customers
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2003, No 115
Gazette.govt.nz —
NZ Gazette 2003, No 115
β¨ LLM interpretation of page content
π
Disclosure of Performance Measures Pursuant to Regulation 22
(continued from previous page)
π Trade, Customs & IndustryElectricity, Performance Measures, Faults, SAIDI, Powerco