ELECTRICITY INVERCARGILL LIMITED LINE BUSINESS

RELIABILITY PERFORMANCE MEASURES

PURSUANT TO REGULATION 22 OF THE ELECTRICITY (INFORMATION DISCLOSURE) REGULATIONS 1999 AS AMENDED BY THE ELECTRICITY (INFORMATION DISCLOSURE) AMENDMENT REGULATIONS 2000

Reliability Statistics For Years Ending 31 March 1999, 2000, 2001 and 2002

Class A B C D E F G TOTAL
Interruptions
1998/99 - 16 36 1 - - 1 54
1999/00 - 18 22 - - - - 40
2000/01 - 11 29 - - - - 40
2001/02 - 11 22 2 - - - 35
Predicted 2002/2003 - 10 23 - - - - 33
5-Year Average Target - 9 21 - - - - 30

| SAIDI | | | | | | | | |
| 1998/99 | - | 7.7 | 43.4| 51.6| - | - | 1.3 | 104.0 |
| 1999/00 | - | 4.7 | 29.0| - | - | - | - | 33.7 |
| 2000/01 | - | 4.0 | 31.0| - | - | - | - | 35.0 |
| 2001/02 | - | 4.0 | 32.0| 59.8| - | - | - | 95.8 |
| Predicted 2002/2003| - | 3.6 | 28.2| - | - | - | - | 31.8 |
| 5-Year Average Target | - | 3.2 | 25.7| - | - | - | - | 28.9 |

| SAIFI | | | | | | | | |
| 1998/99 | - | 0.07| 1.27| 1.01| 0.06| - | - | 2.41 |
| 1999/00 | - | 0.11| 0.53| - | - | - | - | 0.64 |
| 2000/01 | - | 0.05| 1.07| - | - | - | - | 1.12 |
| 2001/02 | - | 0.04| 1.12| 1.71| - | - | - | 2.87 |
| Predicted 2002/2003| - | 0.04| 1.01| - | - | - | - | 1.05 |
| 5-Year Average Target | - | 0.04| 0.92| - | - | - | - | 0.96 |

| CAIDI | | | | | | | | |
| 1998/99 | - | 110.3| 34.1| 51.0| - | - | 22.0| 43.1 |
| 1999/00 | - | 42.5| 54.8| - | - | - | - | 52.7 |
| 2000/01 | - | 80.4| 28.9| - | - | - | - | 31.2 |
| 2001/02 | - | 98.8| 28.5| 35.0| - | - | - | 33.3 |
| Predicted 2002/2003| - | 89.0| 28.0| - | - | - | - | 30.4 |
| 5-Year Average Target | - | 88.0| 28.0| - | - | - | - | 30.3 |

Faults by Voltage

Faults by Voltage 66kV 33kV 11kV Total
OH per 100km
1998/99 - - 48.9 48.7
1999/00 - - 17.9 17.9
2000/01 - - 38.8 38.6
2001/02 - - 37.6 36.9

| UG per 100km |
| 1998/99 | - | - | 2.5 | 2.2 |
| 1999/00 | - | - | 4.8 | 4.2 |
| 2000/01 | - | - | 5.4 | 4.7 |
| 2001/02 | - | - | 4.4 | 3.8 |

| Total per 100km |
| 1998/99 | - | - | 2.5 | 2.2 |
| 1999/00 | - | - | 4.8 | 4.2 |
| 2000/01 | - | - | 5.4 | 4.7 |
| 2001/02 | - | - | 12.2 | 10.8 |
| Predicted 2002/2003 | - | - | 12.2 | 10.8 |
| 5-Year Average Target | - | - | 11.1 | 9.8 |

Class C Interruptions Not Restored in 3 hours: Nil
Class C Interruptions Not Restored in 24 hours: Nil



Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2002, No 91


Gazette.govt.nz PDF NZ Gazette 2002, No 91





✨ LLM interpretation of page content

πŸ—οΈ Reliability Performance Measures for Electricity Invercargill Limited Line Business (continued from previous page)

πŸ—οΈ Infrastructure & Public Works
Electricity, Reliability Statistics, Interruptions, SAIDI, SAIFI, CAIDI, Faults by Voltage, Invercargill