VECTOR Limited

Electricity Lines Business

Reliability Performance Measures To Be Disclosed By Lines Owners (Other Than Transpower) - continued

For the year ended 31 March 2002

FIRST SCHEDULE – PART 5 - CONTINUED

  1. Faults per 100 circuit kilometres of prescribed voltage electric lines
2002 2001 2000 1999
(a) The total number of faults 9.36 10.68 10.51 12.30
2003
(b) The targeted number of faults 9.30
2007 2006 2005 2004 2003
(c) The average number of faults 6.63 7.13 7.91 8.80 9.33

(d) Breakdown of (a) to (c) according to line voltage:

6.6kV 11kV 22kV 33kV 110kV Total
(a) 2002 1.53 10.17 2.37 5.34 13.88 9.36
(b) 2003 3.05 10.32 4.74 2.85 6.17 9.30
(c) 2003 2.29 10.24 3.56 4.10 10.02 9.33
(c) 2004 3.05 9.75 5.14 2.67 6.17 8.80
(c) 2005 3.05 8.75 5.14 2.32 5.40 7.91
(c) 2006 1.53 7.92 4.35 2.14 4.63 7.13
(c) 2007 0.00 7.38 3.56 2.14 4.63 6.63
  1. Number of faults per 100 kilometres of prescribed voltage underground cables
6.6kV 11kV 22kV 33kV 110kV Total
2002 0.00 7.90 2.43 4.68 6.17 7.06
2001 1.65 6.64 7.13 5.03 3.00 6.26
2000 1.00 7.84 5.27 2.52 1.46 6.45
1999 1.24 9.72 6.76 3.05 6.12 7.92
  1. Number of faults per 100 kilometres of prescribed voltage overhead lines
6.6kV 11kV 22kV 33kV 110kV Total
2002 3.76 14.15 0.00 8.77 23.73 14.09
2001 3.54 20.22 0.00 13.15 23.73 19.56
2000 5.01 20.53 0.00 7.25 0.25 19.13
1999 4.35 23.69 0.00 10.83 0.22 21.87


Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2002, No 124


Gazette.govt.nz PDF NZ Gazette 2002, No 124





✨ LLM interpretation of page content

🏭 Vector Limited Financial Statements (continued from previous page)

🏭 Trade, Customs & Industry
Electricity, Financial Performance, Efficiency Measures, Return on Investment, Line Costs, Vector Limited