β¨ Electricity Performance Statistics
NEW ZEALAND GAZETTE
No. 96
| | Years ended 31 March |
| --- | --- | --- | --- | --- |
| | 2000 | 1999 | 1998 | 1997 |
| - 33kV | 0 | 4.76 | 4.4 | 0 |
| - 11kV | 4.53 | 3.3 | 3.4 | 5.2 |
| Total | 4.16 | 3.43 | 3.5 | 4.5 |
(7) Total number of faults per 100 circuit kilometres
of overhead prescribed voltage electric lines
| | - 33kV | 2.8 | 4.3 | 4.6 | 7.3 |
| | - 11kV | 7.8 | 13.8 | 11.7 | 11.7 |
| Total | 7.3 | 12.85 | 11 | 11.3 |
(8) The SAIDI for total of interruptions
| | 100.6 | 201.85 | 140 | 177 |
(9) SAIDI targets for the following financial year
(a) Planned Interruption by the line owner
| Class B | 55 | 60 |
(b) Unplanned Interruption originating from the works of the line owner
| Class C | 85 | 100 |
(10) Average SAIDI Interruption targets for the following financial year and subsequent 4 financial years
(a) Planned Interruption by the line owner
| Class B | 53 | 58 |
(b) Unplanned Interruption originating from the works of the line owner
| Class C | 81 | 96 |
(11) The SAIDI for total of interruptions within each interruption class
| | Class A | 0 | 0 | 0 | 0 |
| | Class B | 39.45 | 57.15 | 55 | 77.9 |
| | Class C | 61.15 | 144.7 | 84.2 | 95.5 |
| | Class D | 0 | 0 | 0 | 3.6 |
| | Class E | 0 | 0 | 0 | 0 |
| | Class F | 0 | 0 | 0 | 0 |
| | Class G | 0 | 0 | 0 | 0 |
(12) The SAIFI for total of interruptions
| | 2.47 | 3.47 | 2.6 | 3.5 |
(13) SAIFI targets for the following financial year
(a) Planned Interruption by the line owner
| Class B | 0.36 | 0.39 |
(b) Unplanned Interruption originating from the works of the line owner
| Class C | 2.30 | 2.70 |
(14) Average SAIFI targets for the following financial year and subsequent 4 financial years
(a) Planned Interruption by the line owner
| Class B | 0.35 | 0.38 |
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2000, No 96
Gazette.govt.nz —
NZ Gazette 2000, No 96
β¨ LLM interpretation of page content
πΎ
Disclosure of financial and efficiency performance measures for Electricity
(continued from previous page)
πΎ Primary Industries & ResourcesElectricity, Financial Performance, Efficiency, Regulation 22, Reliability, Interruptions, Faults, SAIDI, SAIFI