WAIPA NETWORKS LIMITED - LINES BUSINESS

2000 1999 1998 1997

Disclosure of reliability performance measures under regulation 22 of the Electricity (Information Disclosure) Regulations 1999 as amended by the Electricity (Information Disclosure) Amendment Regulations 2000.

1 Total number of interruptions

  • Class A - Planned - by Transpower: 0 | 0 | 0 | 0
  • Class B - Planned - by Line Owners: 223 | 217 | 249 | 234
  • Class C - Unplanned - by Line Owners: 107 | 149 | 117 | 156
  • Class D - Unplanned - by Transpower: 2 | 0 | 1 | 2
  • Class E - Unplanned - by ECNZ: 0 | 0 | 0 | 0
  • Class F - Unplanned - by other generation: 0 | 0 | 0 | 0
  • Class G - Any other loss of supply: 0 | 0 | 0 | 0

Total: 332 | 366 | 367 | 392

2 Interruption targets for 2000 / 2001

  • Class B - Planned - by Line Owners: 200
  • Class C - Unplanned - by Line Owners: 100

3 Average interruption targets for 2000 / 2001 to 2004 / 2005 years

  • Class B - Planned - by Line Owners: 160
  • Class C - Unplanned - by Line Owners: 86

4 *Proportion of Class C interruptions not restored within: (=(a/b)100)**

  • 3 Hours

    • a = number of interruptions restored within 3: 19 (2000), 25 (1999)
    • b = Total number of Class C interruptions: 107 (2000), 149 (1999)
    • Proportion: 18% (2000), 17% (1999)
  • 24 Hours

    • a = number of interruptions restored within 24: 0 (2000), 0 (1999)
    • b = Total number of Class C interruptions: 107 (2000), 149 (1999)
    • Proportion: 0% (2000), 0% (1999)

5 (a) The total number of faults per 100 circuit kilometres of prescribed voltage electric line

  • 11kV: 7.91 (2000), 11.07 (1999), 8.77 (1998), 11.73 (1997)

(b) Target for 2000 / 2001 year

  • 11kV: 7.39

(c) Average Target for 2000 / 2001 to 2004 / 2005 years

  • 11kV: 6.36

6 The total number of faults per 100 circuit kilometres of underground prescribed voltage electric line

  • 11kV: 2.27 (2000), 0.00 (1999), 0.00 (1998), 0.00 (1997)

7 The total number of faults per 100 circuit kilometres of overhead prescribed voltage electric line

  • 11kV: 8.10 (2000), 11.43 (1999), 9.05 (1998), 12.08 (1997)

8 The SAIDI for the total number of interruption

  • SAIDI: 300.44 (2000), 242.23 (1999), 255.21 (1998), 353.09 (1997)

9 SAIDI targets for 2000 / 2001

  • Class B - Planned - by Line Owners: 64.00
  • Class C - Unplanned - by Line Owners: 132.00


Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2000, No 83


Gazette.govt.nz PDF NZ Gazette 2000, No 83





✨ LLM interpretation of page content

🏭 Financial Statements for Waipa Networks Limited (continued from previous page)

🏭 Trade, Customs & Industry
31 March 2000
Financial Statements, Balance Sheet, Assets, Liabilities, Waipa Networks Limited, Statistics, System Length, Transformer Capacity, Maximum Demand, Electricity Supply, Customers