β¨ Electricity Reliability Performance Measures
13 SEPTEMBER NEW ZEALAND GAZETTE 3263
BULLER ELECTRICITY LIMITED β LINE BUSINESS
10 Average SAIDI targets for 2000/2001 to 2004/2005 years
Class B - Planned by Line Owners 141 125 120 115
Class C - Unplanned by Line Owners 118 250 250 250
11 The SAIDI for the total number of interruptions within each interruption class
Class A - Planned by Transpower 0 0 0 0
Class B - Planned by Line Owners 218.41 147.88 123.16 210.19
Class C - Unplanned by Line Owners 146.51 233.63 201.61 265.89
Class D - Unplanned by Transpower 0.32 0 45.03 121.00
Class E - Unplanned by ECNZ 0 0 0 0
Class F - Unplanned by other generator 0 0 0 0
Class G - Any Other Loss of Supply 0.64 0 0 0.02
12 The SAIFI for the total number of Interruptions 3.11 3.30 4.90 7.41
13 SAIFI Targets for 2000/2001
Class B - Planned by Line Owners 0.90
Class C - Unplanned by Line Owners 2.00
14 Average SAIFI targets for 2000/2001 to 2004/2005 years
Class B - Planned by Line Owners 0.80 0.83 0.80 0.78
Class C - Unplanned by Line Owners 1.80 2.30 2.30 2.30
15 The SAIFI for the total number of interruptions within each interruption class
Class A - Planned by Transpower 0 0 0 0
Class B - Planned by Line Owners 0.95 0.91 0.79 0.82
Class C - Unplanned by Line Owners 2.15 2.39 3.11 2.59
Class D - Unplanned by Transpower 0.01 0 1.00 4.00
Class E - Unplanned by ECNZ 0 0 0 0
Class F - Unplanned by other generator 0 0 0 0
Class G - Any Other Loss of Supply 0 0 0 0
16 The CAIDI for the total number of interruption 117.0 115.7 75.50 80.63
17 CAIDI targets for 2000/2001
Class B - Planned by Line Owners 209
Class C - Unplanned by Line Owners 71
18 Average CAIDI Target for 2000/2001 to 2004/2005 years
Class B - Planned by Line Owners 177 160 160 160
Class C - Unplanned by Line Owners 65 97 97 97
19 The CAIDI for the total number of interruptions within each interruption class
Class A - Planned by Transpower 0 0 0 0
Class B - Planned by Line Owners 230 163.14 156.41 256.79
Class C - Unplanned by Line Owners 68 97.68 64.83 102.83
Class D - Unplanned by Transpower 27 0 45.0 30.25
Class E - Unplanned by ECNZ 0 0 0 0
Class F - Unplanned by other generator 0 0 0 0
Class G - Any Other Loss of Supply 340 0 0 10.0
Next Page →
Online Sources for this page:
VUW Te Waharoa —
NZ Gazette 2000, No 129
Gazette.govt.nz —
NZ Gazette 2000, No 129
β¨ LLM interpretation of page content
π
Notes to and forming part of the Financial Statements for Buller Electricity Limited
(continued from previous page)
π Trade, Customs & IndustryReliability Performance Measures, Electricity, Interruptions, Faults, SAIDI, Targets, Class A, Class B, Class C, Class D, Class E, Class F, Class G, 11kV, 33kV, Underground, Overhead