NEW ZEALAND GAZETTE
No. 108

THE POWER COMPANY LIMITED
RELIABILITY PERFORMANCE MEASURES
(LINE BUSINESS)

PURSUANT TO REGULATION 22 OF THE ELECTRICITY (INFORMATION DISCLOSURE) REGULATIONS 1999 AS AMENDED BY THE ELECTRICITY (INFORMATION DISCLOSURE) AMENDMENT REGULATIONS 2000

18.0 RELIABILITY STATISTICS FOR YEARS ENDING 31 MARCH 1997, 1998, 1999 AND 2000

Class A B C D E F G TOTAL
Interruptions
1996/97 0 439 483 3 0 0 0 925
1997/98 0 545 545 0 0 0 0 1,090
1998/99 0 466 486 0 0 0 0 953
1999/00 0 424 488 1 0 1 2 916
Predicted 2000/2001 420 473
5-Year Average Target 400 430
SAIDI
1996/97 0 65.7 418.4 8.2 0 0 0 492.3
1997/98 0 92.9 651.5 0 0 0 0 744.4
1998/99 0 60.9 276.5 17.3 0 0 0 354.7
1999/00 0 73.9 339.6 51.3 0 1.1 0.6 446.4
Predicted 2000/2001 57.5 300.0
5-Year Average Target 54.0 275.0
SAIFI
1996/97 0 0.532 5.081 1.002 0 0 0 6.615
1997/98 0 0.79 6.752 0 0 0 0 7.542
1998/99 0 0.55 5.490 0.340 0 0 0 6.380
1999/00 0 0.56 5.890 0.280 0 0.04 0.01 6.780
Predicted 2000/2001 0.53 5.100
5-Year Average Target 0.50 5.000
CAIDI
1996/97 0 123.4 82.3 8.2 0 0 0 74.4
1997/98 0 117.6 96.5 0 0 0 0 98.7
1998/99 0 110.6 50.4 51.0 0 0 0 55.6
1999/00 0 131.9 57.7 180.9 0 30.0 44.4 68.8
Predicted 2000/2001 108.5 58.8
5-Year Average Target 108.0 55.0

Faults by Voltage

66kV 33kV 11kV Total
OH per 100km
1996/97 0.40 2.20 7.30 6.70
1997/98 0.80 5.50 7.50 7.20
1998/99 3.17 3.13 7.49 7.02
1999/00 2.33 6.20 7.84 7.44
UG per 100km
1996/97 0 0 26.90 25.80
1997/98 0 125 9.20 11.20
1998/99 0 0 4.40 4.26
1999/00 0 0 8.50 8.25
Total per 100km
1996/97 0.40 2.10 7.40 6.80
1997/98 0.80 5.70 7.60 7.20
1998/99 3.17 3.13 7.47 7.00
1999/00 2.33 6.18 7.85 7.45
Predicted 2000/2001 3.17 3.13 7.46 7.02
5-Year Average Target 2.78 2.5 6.80 6.36
Class C Interruptions Not Restored in 3 hours 3.48%
Class C Interruptions Not Restored in 24 hours 0%


Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 2000, No 108


Gazette.govt.nz PDF NZ Gazette 2000, No 108





✨ LLM interpretation of page content

πŸ’° Disclosure of Financial Statements under Electricity (Information Disclosure) Regulations (continued from previous page)

πŸ’° Finance & Revenue
Financial Performance Measures, Intangible Assets, Subvention Payments, System Fixed Assets, Return on Funds, Return on Equity, Return on Investment, Energy Delivery Efficiency, Load Factor, Loss Ratio, Capacity Utilisation, System Length, Overhead Lines, Underground Cables, TX Capacity, Maximum Demand, Electricity Supplied, Electricity Conveyed, Total Customers

πŸ—οΈ Reliability Performance Measures for The Power Company Limited

πŸ—οΈ Infrastructure & Public Works
Electricity, Reliability Statistics, SAIDI, SAIFI, CAIDI, Faults by Voltage, Interruptions, Predicted Performance, Performance Targets