26 NOVEMBER NEW ZEALAND GAZETTE 4287

11 The SAIDI for the total number of interruptions within each interruption class

Year Ended 31-Mar-99 Year Ended 31-Mar-98 Year Ended 31-Mar-97 Year Ended 31-Mar-96
Class A - Planned interruptions caused by TransPower 0 13.13 0.1
Class B - Planned interruptions by Westpower 138.00 211.48 158.9
Class C - Unplanned interruptions by Westpower 103.00 133.29 240.2
Class D - Unplanned interruptions by TransPower 3.40 25.19 36.7
Class E - Unplanned interruptions by ECNZ Generation 0 0 0
Class F - Unplanned interruptions by Westpower Generation 0 1.07 0
Class G - Other interruptions(planned Westpower Generation) 0 0.07 0

12 The SAIFI for the total number of interruptions

2.148 | 4.05 | 3.38 | 5.6 |

13 SAIFI targets for the following financial year

(a) Planned Interruption by the line owner - Class B 0.35

(b) Unplanned Interruption originating from the works of the line owner - Class C 2

14 Average SAIFI targets for the following financial year and subsequent 4 financial years

(a) Planned Interruption by the line owner - Class B 0.3

(b) Unplanned Interruption originating from the works of the line owner - Class C 1.5

15 The SAFI for the total number of interruptions within each interruption class

Year Ended 31-Mar-99 Year Ended 31-Mar-98 Year Ended 31-Mar-97 Year Ended 31-Mar-96
Class A - Planned interruptions caused by TransPower 0 0.1 0
Class B - Planned interruptions by Westpower 0.614 0.96 0.68
Class C - Unplanned interruptions by Westpower 1.454 1.99 1.84
Class D - Unplanned interruptions by TransPower 0.08 0.97 0.86
Class E - Unplanned interruptions by ECNZ Generation 0 0 0
Class F - Unplanned interruptions by Westpower Generation 0 0.03 0
Class G - Other interruptions(planned Westpower Generation) 0 0 0

16 The CAIDI for the total number of interruptions

113.25 | 94.87 | 129.09 | 101.6 |

17 CAIDI targets for the following financial year

(a) Planned Interruption by the line owner - Class B 220

(b) Unplanned Interruption originating from the works of the line owner - Class C 75

18 Average CAIDI targets for the following financial year and subsequent 4 financial years

(a) Planned Interruption by the line owner - Class B 200

(b) Unplanned Interruption originating from the works of the line owner - Class C 65

19 The CAIDI for the total number of interruptions within each interruption class

Year Ended 31-Mar-99 Year Ended 31-Mar-98 Year Ended 31-Mar-97 Year Ended 31-Mar-96
Class A - Planned interruptions caused by TransPower 0 130.25 40
Class B - Planned interruptions by Westpower 221 220.82 235.27
Class C - Unplanned interruptions by Westpower 84 66.85 130.35
Class D - Unplanned interruptions by TransPower 41.75 26.03 42.67
Class E - Unplanned interruptions by ECNZ Generation 0 0 0
Class F - Unplanned interruptions by Westpower Generation 0 35.67 0
Class G - Other interruptions(planned Westpower Generation) 0 0 0


Next Page →

PDF embedding disabled (Crown copyright)

View this page online at:


VUW Te Waharoa PDF NZ Gazette 1999, No 180


NZLII PDF NZ Gazette 1999, No 180





✨ LLM interpretation of page content

πŸ—οΈ Westpower Limited Electricity Interruption and Fault Statistics (continued from previous page)