NEW ZEALAND GAZETTE
19 NOVEMBER
STATEMENT OF PERFORMANCE MEASURES AND STATISTICS
for the year ended 31 March 1999
RELIABILITY PERFORMANCE MEASURES (continued)
| Interruption Class | 1999 | 1998 | 1997 | 1996 | 1995 | |
|---|---|---|---|---|---|---|
| A | Planned Interruption by Transpower | Number | 1 | 5 | 2 | 0 |
| SAIDI | 1.7 | 31.5 | 26.9 | 0 | ||
| SAIFI | 0.00 | 0.32 | 0.24 | 0 | ||
| CAIDI | 37.0 | 99.9 | 112.0 | 0 |
| B | Planned Interruption by Other Line Owner | Number | 37 | 47 | 43 | 25 | 34 |
| | | SAIDI | 157.2 | 245.7 | 98.6 | 166 | 201 |
| | | SAIFI | 0.80 | 2.09 | 0.93 | 1.04 | 1.20 |
| | | CAIDI | 187.2 | 117.1 | 106.0 | 160 | 167 |
| C | Unplanned Interruption by Other Line Owner | Number | 99 | 84 | 178 | 59 | 88 |
| | | SAIDI | 361.6 | 989.7 | 748.0 | 499 | 1081 |
| | | SAIFI | 7.80 | 7.31 | 7.09 | 4.40 | 2.31 |
| | | CAIDI | 46.3 | 135.4 | 105.5 | 115 | 469 |
| D | Unplanned Interruption by Transpower | Number | 2 | 5 | 0 | 2 | 1 |
| | | SAIDI | 81.1 | 157.4 | 0 | 29 | 5 |
| | | SAIFI | 2.10 | 2.59 | 0 | 2.20 | 0.05 |
| | | CAIDI | 37.9 | 60.8 | 0 | 26 | 5 |
| E | Unplanned Interruption by ECNZ | Number | 0 | 0 | 0 | 1 | 0 |
| | | SAIDI | 0 | 0 | 0 | 7 | 0 |
| | | SAIFI | 0 | 0 | 0 | 1.00 | 0 |
| | | CAIDI | 0 | 0 | 0 | 7 | 0 |
| F | Unplanned Interruption by any other generator | Number | 0 | 0 | 0 | 0 | 0 |
| | | SAIDI | 0 | 0 | 0 | 0 | 0 |
| | | SAIFI | 0 | 0 | 0 | 0 | 0 |
| | | CAIDI | 0 | 0 | 0 | 0 | 0 |
| G | Unplanned Interruption not resulting from above | Number | 0 | 0 | 0 | 0 | 0 |
| | | SAIDI | 0 | 0 | 0 | 0 | 0 |
| | | SAIFI | 0 | 0 | 0 | 0 | 0 |
| | | CAIDI | 0 | 0 | 0 | 0 | 0 |
| Total | | Number | 139 | 141 | 223 | 87 | 125 |
| | | SAIDI | 602 | 1,424 | 872.8 | 729 | 1340 |
| | | SAIFI | 10.80 | 12.31 | 8.26 | 8.60 | 4.06 |
| | | CAIDI | 55.5 | 115.7 | 105.7 | 85 | 330 |
- SAIDI - System Average Interruption Duration Index (minutes per customer per year)
- SAIFI - System Average Interruption Frequency Index (interruptions per customer per year)
- CAIDI - Customer Average Interruption Duration Index (minutes per customer interrupted)
Next Page →
PDF embedding disabled (Crown copyright)
View this page online at:
VUW Te Waharoa —
NZ Gazette 1999, No 175
NZLII —
NZ Gazette 1999, No 175
β¨ LLM interpretation of page content
ποΈ
Reliability Performance Measures for Electricity Lines for the year ended 31 March 1999
(continued from previous page)
ποΈ Infrastructure & Public WorksElectricity, Reliability, Faults, Overhead lines, Underground lines, Prescribed voltage lines, SAIDI, SAIFI, CAIDI