3016 NEW ZEALAND GAZETTE No. 125

3.4 Schedule 1 – PART 5 (continued)

UnitedNetworks 2000 2001 2002 2003 2004
For the year ended 31 March
2 Interruption Targets
Planned Class B 985
Unplanned Class C 1,373
3 Average Interruption Targets
Planned Class B 985 968 951 934 917
Unplanned Class C 1,373 1,344 1,315 1,286 1,257
5 Total Number of Faults Targeted 1,366
110kV -
66kV 4
33kV 73
11kV 1,289
5 Average Number of Faults 1,366 1,307 1,248 1,189 1,130
110kV - - - - -
66kV 4 4 4 4 4
33kV 73 73 73 73 73
11kV 1,289 1,230 1,171 1,112 1,053
9 SAIDI Targets
Planned Class B 23.0
Unplanned Class C 98.0
10 Average SAIDI Targets
Planned Class B 23.0 22.0 221.0 20.0 19.0
Unplanned Class C 98.0 96.0 93.0 91.0 88.0
13 SAIFI Targets
Planned Class B 0.18
Unplanned Class C 1.82
14 Average SAIFI Targets
Planned Class B 0.18 0.18 0.18 0.17 0.17
Unplanned Class C 1.82 1.81 1.81 1.80 1.77
17 CAIDI Targets
Planned Class B 127.78
Unplanned Class C 53.85
18 Average CAIDI Targets
Planned Class B 127.78 124.29 120.00 116.28 112.43
Unplanned Class C 53.85 52.98 51.52 50.61 49.69


Next Page →

PDF embedding disabled (Crown copyright)

View this page online at:


VUW Te Waharoa PDF NZ Gazette 1999, No 125


NZLII PDF NZ Gazette 1999, No 125





✨ LLM interpretation of page content

πŸ’° Performance Measures and Statistics for Line Owners (continued from previous page)

πŸ’° Finance & Revenue
Electricity reliability, Interruptions, Faults, SAIDI, SAIFI, CAIDI, UnitedNetworks