2864

NEW ZEALAND GAZETTE

No. 120

Reliability Performance Measures for the Year Ended 31 March 1996

Consumer Connections Line 33kV Line 11kV Line 6.6kV Cable 33kV Cable 11kV Cable 6.6kV Total Density Con/km
At start of period 49,730 149.9 235.8 485.0 75.2 20.2 228.7 1,195
At end of period 49,837 149.9 236.5 488.1 75.2 20.4 229.5 1,200
Average 49,784 149.9 236.1 486.6 75.2 20.3 229.1 1,197
Totals 872.6 324.6 1,197
Reliability Measure SAIDI Cons Mins SAIDI Mins/Cons SAIFI Cons Int SAIFI Int/Cons CAIDI Mins/Int No of Interruptions Class
Distributor Planned 68,570 1.38 1,230 0.02 55.70 10 B
Distributor Unplanned 897,355 18.03 28,058 0.56 32.00 91 C
Subtotal 965,925 19.40 29,288 0.59 33.00 101
Transpower Planned - - - - - A
Transpower Unplanned - - - - - D
Subtotal - - - - -
ECNZ Planned - - - - - E
ECNZ Unplanned - - - - -
Subtotal - - - - -
Other Gen Planned - - - - - F
Other Gen Unplanned - - - - -
Other Than Above - - - - - G
Subtotal - - - - -
TOTAL 965,925 19.40 29,288 0.59 33.00 101
Faults by Voltage OH Faults OH Length km OH per 100 km Cable Faults UG Length km UG per 100 km
33kV 6 149.9 4.0 4 75.2 5.3
11kV 43 236.1 18.2 2 20.3 9.9
6.6kV 36 486.6 7.4 4 229.1 1.7
TOTAL 85 872.6 9.7 10 324.6 3.1

Total Lines and Cables

Total Faults
95

Total Length in km
1,197

Faults per 100 km
7.9



Next Page →

PDF embedding disabled (Crown copyright)

View this page online at:


VUW Te Waharoa PDF NZ Gazette 1999, No 120


NZLII PDF NZ Gazette 1999, No 120





✨ LLM interpretation of page content

πŸ’° Reliability Performance Measures for Electricity (continued from previous page)

πŸ’° Finance & Revenue
Reliability Measures, Statistics, Electricity, Regulation 22