2256 NEW ZEALAND GAZETTE No. 96

BULLER ELECTRICITY LIMITED

PERFORMANCE MEASURES

YEAR ENDED MARCH 31 1997

  1. RELIABILITY PERFORMANCE MEASURES

  2. Total Number of Interruptions

1997 1996 1995
Class A 0 0 0
Class B 34 38 33
Class C 64 144 131
Class D 4 2 2
Class E 0 0 0
Class F 0 0 0
Class G 1 0 0
Total 103 184 166
  1. Total Number of Faults per 100 circuit KM of Electric Line

    • 22.18
  2. Total Number of Faults per 100 circuit KM of Underground Line 11kV

  3. Total Number of Faults per 100 circuit KM of Overhead Line

    • 33kV: 22.27, 8.08
    • 11kV: 27.07, 33.09, 31.16
1997 1996 1995
22.18 32.38 31.50
0 0 16.81
33kV 22.27 N/A 0.39
11kV 27.07 55.3 30.91
  1. The SAIDI for the total of Interruptions

    • 597.10
  2. The SAIDI for the total number of Interruptions within each Interruption Class

1997 1996 1995
Class A 0 0 0
Class B 210.19 397.08 224.74
Class C 265.89 211.0 331.94
Class D 121.00 41.83 19.12
Class E 0 0 0
Class F 0 0 0
Class G 0.02 0 0
  1. The SAIFI for the total number of Interruptions

    • 7.41
  2. The SAIFI for the total number of Interruptions within each Interruption Class

1997 1996 1995
Class A 0 0 0
Class B 0.82 1.66 0.69
Class C 2.59 1.15 3.04
Class D 4.00 1.00 1.00
Class E 0 0 0
Class F 0 0 0
Class G 0 0 0
  1. The CAIDI for the total of all Interruptions

    • 80.63
  2. The CAIDI for the total number of Interruptions within each Interruption Class

1997 1996 1995
Class A 0 0 0
Class B 256.79 239.04 323.42
Class C 102.83 183.05 109.04
Class D 30.25 41.83 19.12
Class E 0 0 0
Class F 0 0 0
Class G 10.0 0 0
  1. Disclosure of ODV Valuation
    • Line Business Asset Value: $12.93 M

P ROSELLI

DATE: 30.7.97



Next Page →

PDF embedding disabled (Crown copyright)

View this page online at:


VUW Te Waharoa PDF NZ Gazette 1997, No 96


NZLII PDF NZ Gazette 1997, No 96





✨ LLM interpretation of page content

🏭 Certification of Buller Electricity Limited Financial Performance Measures (continued from previous page)

🏭 Trade, Customs & Industry
30 July 1997
Financial Performance, Certification, Electricity, Audit, Buller Electricity Limited
  • P Roselli