First Schedule Pt III Energy Delivery Efficiency Performance Measures and Statistics

1996

1 a) Load factor 58%
b) Loss ratio 5%
c) Capacity utilization 35%

2 a)b)c) Circuit km

Overhead Underground Total
33 kV 186.40 61.60 248.00
11 kV 1,772.80 340.90 2,113.70
400 V 840.70 352.70 1,193.40
TOTAL 2,799.90 755.20 3,555.10

d) Transformer capacity 471,980 kVA
e) Maximum demand 163,700 kW
f) Total Electricity supplied from the system (excluding losses) 791,882,000 kWhs
g) Total amount of electricity conveyed through the system for other ER's and generators 50,967,000 kWhs
h) Total customers 64,961

1995

1 a) Load factor 59%
b) Loss ratio 5%
c) Capacity utilization 34%

2 a)b)c) Circuit km

Overhead Underground Total
33 kV 184.37 58.94 243.31
11 kV 1,772.03 336.96 2,108.99
400 V 840.38 336.74 1,177.12
TOTAL 2,796.78 732.64 3,529.42

d) Transformer capacity 452,617 kVA
e) Maximum demand 153,700 kW
f) Total Electricity supplied from the system (excluding losses) 753,646,133 kWhs
g) Total amount of electricity conveyed through the system for other ER's and generators 19,455,380 kWhs
h) Total customers 63,323



Next Page →

PDF embedding disabled (Crown copyright)

View this page online at:


VUW Te Waharoa PDF NZ Gazette 1996, No 165


NZLII PDF NZ Gazette 1996, No 165





✨ LLM interpretation of page content

πŸ’° Auditor Certification of WEL Energy Group Limited Financial Statements (continued from previous page)

πŸ’° Finance & Revenue
14 August 1996
Audit, Financial Statements, WEL Energy Group, Electricity Regulations, Coopers & Lybrand

🌾 Energy Delivery Efficiency Performance Measures and Statistics for 1996

🌾 Primary Industries & Resources
Load factor, Loss ratio, Capacity utilization, Circuit km, Transformer capacity, Maximum demand, Electricity supply, Customers

🌾 Energy Delivery Efficiency Performance Measures and Statistics for 1995

🌾 Primary Industries & Resources
Load factor, Loss ratio, Capacity utilization, Circuit km, Transformer capacity, Maximum demand, Electricity supply, Customers