NEW ZEALAND GAZETTE
WESTPOWER LIMITED
SYSTEM RELIABILITY
Disclosure by line owners of reliability performance measures as required by Regulation 16 of the Electricity (Information Disclosure) Regulations 1994
Part IV 1. of the first schedule
Total number of interruptions, together with a breakdown of that total according to interruption class
| Year ended 31-Mar-95 | Year ended 31-Mar-96 | |
|---|---|---|
| Class A - Planned interruptions caused by Trans Power | 0 | 0 |
| Class B - Planned interruptions by Westpower | 98 | 71 |
| Class C - Unplanned interruptions by Westpower | 220 | 135 |
| Class D - Unplanned interruptions caused by Trans Power | 10 | 6 |
| Class E - Unplanned interruptions caused by ECNZ generation | 0 | 0 |
| Class F - Unplanned interruptions caused by Westpower generation | 8 | 10 |
| Class G - Other interruptions (Planned Westpower generation) | 0 | 0 |
| Total interruptions | 336 | 222 |
Part IV 2. of the first schedule
The total number of faults per 100 circuit kilometres of prescribed voltage electric line (Voltage equal to or greater than 3.3 kilovolts)
Total faults per 100 km
| | 12.51 | 8.50 |
Part IV 3. of the first schedule
Total number of faults per 100 kilometres of underground prescribed voltage electric line
| Nominal Line Voltage | Year ended 31-Mar-95 | Year ended 31-Mar-96 |
|---|---|---|
| 66kv / 50kv | 0.00 | 0.00 |
| 33kv | 0.00 | 0.00 |
| 11kV | 17.72 | 18.18 |
| Total faults per 100 km | 17.53 | 17.97 |
Part IV 4. of the first schedule
Total number of faults per 100 kilometres of overhead prescribed voltage electric line
| Year ended 31-Mar-95 | Year ended 31-Mar-96 | |
|---|---|---|
| 66kv / 50kv | 16.83 | 25.21 |
| 33kv | 8.37 | 7.09 |
| 11kv | 12.65 | 8.21 |
| Total faults per 100 km | 12.42 | 8.34 |
Part IV 5. of the first schedule
The SAIDI for the total number of interruptions
| | 646.70 | 835.42 |
Part IV 6. of the first schedule
The SAIDI for the total number of interruptions within each interruption class
| Year ended 31-Mar-95 | Year ended 31-Mar-96 | |
|---|---|---|
| Class A - Planned interruptions caused by Trans Power | 0.00 | 0.00 |
| Class B - Planned interruptions by Westpower | 256.11 | 287.20 |
| Class C - Unplanned interruptions by Westpower | 243.80 | 384.06 |
| Class D - Unplanned interruptions caused by Trans Power | 137.46 | 135.74 |
| Class E - Unplanned interruptions caused by ECNZ generation | 0.00 | 0.00 |
| Class F - Unplanned interruptions caused by Westpower generation | 9.33 | 28.43 |
| Class G - Other interruptions (Planned Westpower generation) | 0.00 | 0.00 |
Next Page →
PDF embedding disabled (Crown copyright)
View this page online at:
VUW Te Waharoa —
NZ Gazette 1996, No 114
NZLII —
NZ Gazette 1996, No 114
β¨ LLM interpretation of page content
ποΈ
Westpower Limited System Reliability
(continued from previous page)
ποΈ Infrastructure & Public WorksReliability Performance, Electricity, Statistics, Westpower Limited