Where the two adjacent compartments have different factors of subdivision, the combined length of the two compartments shall be determined proportionately.
(2) In ships 430 feet (131 metres) in length and upwards, one of the main transverse bulkheads abaft the fore peak shall be fitted at a distance from the forward perpendicular which is not greater than the permissible length.
(3) A main transverse bulkhead may be recessed provided that all parts of the recess lie inboard of vertical surfaces on both sides of the ship, situated at a distance from the shell plating equal to one-fifth the breadth of the ship, as defined in Regulation I (3), and measured at right angles to the centreline at the level of the deepest subdivision loadline.
Any part of a recess which lies outside these limits shall be dealt with as a step in accordance with the following paragraph.
(4) A main transverse bulkhead may be stepped provided that—
(a) The combined length of the two compartments, separated by the bulkhead in question, does not exceed 90 per cent. of the floodable length, or
(b) Additional subdivision is provided in way of the step to maintain the same measure of safety as that secured by a plane bulkhead.
(5) Where a main transverse bulkhead is recessed or stepped, an equivalent plane bulkhead shall be used in determining the subdivision.
(6) If the distance between two adjacent main transverse bulkheads, or their equivalent plane bulkheads, or the distance between the transverse planes passing through the nearest stepped portions of the bulkheads, is less than 10 feet (3·05 metres) plus 2 per cent. of the length of the ship, only one of these bulkheads shall be regarded as forming part of the subdivision of the ship in accordance with the provisions of Regulation IV.
(7) Where a main transverse watertight compartment contains local subdivision and it can be shown to the satisfaction of the Administration that, after any assumed side damage extending over a length of 10 feet (3·05 metres) plus 2 per cent. of the length of the ship, the whole volume of the main compartment will not be flooded, a proportionate allowance may be made in the permissible length otherwise required for such compartment.
In such a case the volume of effective buoyancy assumed on the undamaged side shall not be greater than that assumed on the damaged side.
(8) Where it is proposed to fit watertight decks, inner skins or longitudinal bulkheads, watertight or non-watertight, the Administration shall be satisfied that the safety of the ship will not be diminished in any respect, particularly having in view the possible listing effect of flooding in way of such structural arrangements.
REGULATION VI.
Peak and Machinery Space Bulkheads, Shaft Tunnels, &c.
(1) Every ship shall have a forepeak or collision bulkhead, which shall be watertight up to the bulkhead deck. This bulkhead shall be fitted not less than 5 per cent. of the length of the ship, and not more than 10 feet (3·05 metres) plus 5 per cent. of the length of the ship from the forward perpendicular.
If the ship has a long forward superstructure, the forepeak bulkhead shall be extended weathertight to the deck next above the bulkhead deck. The extension need not be fitted directly over the bulkhead below, provided it is at least 5 per cent. of the length of the ship from the forward perpendicular, and the part of the bulkhead deck which forms the step is made effectively weathertight.
(2) An afterpeak bulkhead, and bulkheads dividing the machinery space, as defined in Regulation I (8), from the cargo and passenger spaces forward and aft, shall also be fitted and made watertight up to the bulkhead deck. The afterpeak bulkhead may, however, be stopped below the bulkhead deck, provided the degree of safety of the ship as regards subdivision is not thereby diminished.
(3) In all cases stern tubes shall be enclosed in watertight spaces. The stern gland shall be situated within a watertight shaft tunnel or other space of such volume that if flooded by leakage through the stern gland the margin line will not be submerged.
Next Page →
PDF embedding disabled (Crown copyright)
View this page online at:
VUW Te Waharoa —
NZ Gazette 1934, No 77
NZLII —
NZ Gazette 1934, No 77
✨ LLM interpretation of page content
🚂
Regulations for Ship Construction
(continued from previous page)
🚂 Transport & CommunicationsShip construction, Subdivision loadline, Bulkhead deck, Margin line, Floodable length, Permeability, Factor of subdivision, Criterion of service