✨ Railway Traffic and Construction Costs




232
THE NEW ZEALAND GAZETTE.
[No. 9

COMPARATIVE STATEMENT of TRAFFIC on ALL SECTIONS, from 1st April, 1886, to 8th January, 1887.

All Sections. Passengers. Season Tickets. Number. Number.
First Class. Second Class. Total. Total. Parcels. Horses. Carriages. Dogs. Total. Drays, &c. Cattle. Calves. Sheep. Pigs. Total.
S. R. S. R.
1887 192,017 373,634 705,530 1,382,100 2603,281 8,772 257,781 6,780 504 17,130 282,195 453 28,756 1,335 595,493 37,366 663,403
1886 224,386 331,040 820,211 1,155,522 2531,159 7,773 238,357 7,100 486 17,753 263,696 518 26,555 1,777 518,266 32,369 579,485
Inc. .. 42,594 .. 176,578 72,122 999 19,424 .. 18 .. 18,499 .. 2,201 .. 77,227 4,997 83,918
Dec. 32,369 .. 114,681 .. .. .. .. 320 .. 623 .. 65 .. 442 .. .. ..

Tons.

All Sections. Chaff, &c. Wool. Firewood. Timber. Grain. Merchandise. Minerals. Total.
Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr.
1887 .. 18,390 0 0 50,927 12 0 57,685 0 0 134,590 9 0 253,400 4 3 244,459 14 2 553,809 15 3 1,313,262 16 0
1886 .. 12,215 0 0 41,363 4 0 64,640 0 0 155,786 11 0 327,520 14 0 272,546 4 1 517,557 2 0 1,391,678 15 1
Increase 6,125 0 0 9,564 8 0 .. .. .. .. 36,252 13 3 ..
Decrease .. .. 6,955 0 0 21,196 2 0 74,120 9 1 28,086 9 3 .. 78,415 19 1

STATEMENT showing Cost of Construction of ALL LINES, GENERAL GOVERNMENT, PROVINCIAL, and DISTRICT RAILWAYS,
to 31st March, 1886, including Expenditure on Harbour Works constructed from the Railway Votes.

Section. Gross Cost of Opened and Unopened Lines. Cost of Opened Lines.
Β£ s. d. Β£ s. d.
Kawakawa 89,441 0 0 89,441 0 0
Whangarei-Kamo .. 68,241 0 0 68,241 0 0
Auckland 1,586,568 0 0 1,545,181 0 0
Waikato-Thames .. 40,050 0 0 ..
Main Trunk Line, North Island 60,780 0 0 ..
Napier .. 571,909 0 0 559,800 0 0
Wellington 907,762 0 0 815,000 0 0
Wanganui 1,368,230 0 0 1,349,900 0 0
Wellington-Manawatu 41,815 0 0 ..
Surveys, North Island 17,129 0 0 ..
Miscellaneous .. 5,168 0 0 ..
Hurunui-Bluff .. 7,643,238 0 0 7,288,049 0 0
Greymouth 196,259 0 0 180,300 0 0
Greymouth-Hokitika 37,777 0 0 ..
Grey Harbour Works 127,230 0 0 ..
Westport .. 214,402 0 0 214,402 0 0
Westport Harbour Works 14,111 0 0 ..
Nelson .. 174,914 0 0 166,700 0 0
Picton .. 219,605 0 0 195,800 0 0
Surveys, Middle Island 36,117 0 0 ..
Miscellaneous .. 5,169 0 0 ..
Stock .. 300,241 0 0 ..
Total 13,726,166 0 0 12,472,814 0 0

J. P. MAXWELL,
General Manager, New Zealand Railways.

Railway Department, 9th February, 1887.



Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 1887, No 9





✨ LLM interpretation of page content

πŸš‚ Comparative Statement of Traffic on All Sections (continued from previous page)

πŸš‚ Transport & Communications
9 February 1887
Railway, Traffic, Passengers, Parcels, Animals, Tons, Chaff, Wool, Firewood, Timber, Grain, Merchandise, Minerals
  • J. P. Maxwell, General Manager, New Zealand Railways

πŸ—οΈ Cost of Construction of All Lines

πŸ—οΈ Infrastructure & Public Works
9 February 1887
Railway, Construction, Cost, Lines, Sections, Gross Cost, Opened Lines, North Island, South Island
  • J. P. Maxwell, General Manager, New Zealand Railways